NalandaBRPNNLUnknown

Construction of HLRCC Bridge (2x16.00m) in 9th km of Hilsa- Noorsarai Road in Nalanda District.

Nalanda·Nalanda·Bihar

Admin Approval

₹556 L

Agreement Amount

₹3.46 Cr

Commencement

25 Aug 2025

Scheduled Completion

24 Nov 2026

Project Details

DivisionNalanda
DistrictNalanda
SchemeNabard RCD
AA Vide No.Letter No. 5007 (S)
AA Date14 Oct 2024
Bridge Type/LengthN/A

Cost & Timeline

Admin. Approval₹556.09 lakh
Agreement Amount₹3.46 Cr
Commencement25 Aug 2025
Scheduled24 Nov 2026
RevisedN/A
Schedule StatusOn schedule

Construction of HLRCC Bridge (2x16.00m) in 9th km of Hilsa- Noorsarai Road in Nalanda District. is a bridge construction project in Nalanda district under the Bihar Rajya Pul Nirman Nigam Limited (BRPNNL), Nalanda. The agreement amount is ₹3.46 Cr, and the project is currently Unknown.

BRPNNL bridges improve rural and inter-district connectivity across Bihar. Other bridge projects in Nalanda district are listed below.

Remarks

1.) Pile work 22/22 Completed. 2.) Pile Cap 3/3 Completed. 3. Pier Shaft 3/3 Completed. 4.) Girder Both Span Competed. 5.) Deck Slab work in Progress.

?

Frequently Asked Questions

QWhat is the current status of "Construction of HLRCC Bridge (2x16.00m) in 9th km of Hilsa- Noorsarai Road in Na"?
Status: Unknown. Physical achievement: N/A. On schedule. Scheduled completion: 24 Nov 2026. This is a BRPNNL bridge and road project in Nalanda, Bihar.
QWhat is the cost of this BRPNNL project?
The agreement amount for this project is ₹3.46 Cr. Administrative approval: ₹556.09 lakh. The project is in Nalanda division, Nalanda district.
QWhich division is this BRPNNL project in?
This project is under BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) Nalanda division in Nalanda district, Bihar. Scheme: Nabard RCD. AA Vide No.: Letter No. 5007 (S).
QWhat does BRPNNL do in Bihar?
BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) is a Bihar government corporation responsible for bridge and road construction across rural and semi-urban Bihar. "Construction of HLRCC Bridge (2x16.00m) in 9th km of Hilsa- " in Nalanda is one of many bridge projects tracked through the Monthly Progress Report (MPR) system monitored on BiharInfraTales.