Champaran(Motihari)·Pachim Champarn·Bihar
Admin Approval
₹862 L
Agreement Amount
₹7.34 Cr
Commencement
27 Sep 2018
Scheduled Completion
26 Dec 2019
1. Diversion completed and Traffic is moving on. 2. Need regular maintenance of diversion during rainy season until get clearance/NOC from concerned department. 3. Due to Flood water overtopped diversion and traffic movement stopped.