Champaran(Motihari)·Pachim Champarn·Bihar
Admin Approval
₹3705 L
Agreement Amount
₹39.55 Cr
Commencement
08 Jun 2024
Scheduled Completion
07 Jun 2026
1. 66/88 Pile completed 2. 10/14 Hammer Head Completed; remaining in progress. 3. P8-P9 Deck slab reinforcement work is in progress * Encroachment removal towards Bettiah side in progress. 4. LA:-Section-21(I) has been completed