Construction of Phase-2 of Central Park, Maur
Tender Description
Construction of Phase-2 of Central Park, Maur
Tender Specifications & Timeline
15 FieldsAward of Contract (AOC) Details
Awardee / Contractor
HARPAL SINGH CONTRACTOR
Award Date: 23-Mar-2026
Completion Period: 120 Days
Contract Financials & Scope
INR 1,468,500
Contract Award Info Updated 23-Mar-2026 07:54 PM by Karnail singh
Total Bidders
2
Winning Bid (L1)
₹14.69 L
Estimated Value (PAC)
₹16.50 L
Margin vs Estimate
-11.00%
L1 to L2 Spread
+7.87%
Completion Period
120 days
AOC Award Date
23-Mar-2026
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | HARPAL SINGH CONTRACTOR#708106 | ₹14.69 L | 0.0% (L1) | -11.00% | Accepted-AOC |
| L2 | GURPREET SINGH CONTRACTOR#708159 | ₹15.84 L | +7.87% | Rejected-Fin | Rejected-Finance |
This urban amenities tender covers construction of Phase-2 of Central Park, Maur , issued by Department of Local Government under reference MC Maur. The estimated contract value is ₹0.17 Cr, and the tender is currently Expired. Following contract finalisation, the work has been awarded to HARPAL SINGH CONTRACTOR for a total value of ₹14.69 L.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in MC Maur. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
2
L1
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
GURPREET SINGH CONTRACTOR #708159 | 31-Dec-2025 12:09 PM | Rejected-Finance Updated: 27-Jan-2026 06:58 PM | 15,84,000.00 | L2 | 2 |
HARPAL SINGH CONTRACTOR #708106 | 31-Dec-2025 10:41 AM | Accepted-AOC Updated: 23-Mar-2026 07:54 PM | 14,68,500.00 | L1 | L1 |
Bid Evaluation Details & Logs
technical bid opening
Date: 06-Jan-2026 12:57 PM
Officer: Karnail singh
ok
technical evaluation
Date: 06-Jan-2026 01:37 PM
Officer: Karnail singh
finance bid opening
Date: 09-Jan-2026 08:06 PM
Officer: Karnail singh
ok
finance evaluation
Date: 27-Jan-2026 06:58 PM
Officer: Karnail singh
About This Procurement Notice
This Punjab state government tender was issued by Department of Local Government. The estimated contract value is ₹16.50 L. Bids must be submitted by 01-Jan-2026 01:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Construction of Phase-2 of Central Park, Maur "?
- The current status of this tender is "Expired". The submission deadline is 01-Jan-2026 01:00 PM. This information is sourced from official government procurement portals.
- QWho issued this Punjab government tender?
- This tender was issued by Department of Local Government. The reference number is MC Maur. It is a Punjab state government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹16.50 L. This is the approximate contract value as disclosed in the official tender document.
- QWho won the contract for this tender?
- The contract for "Construction of Phase-2 of Central Park, Maur" has been awarded to HARPAL SINGH CONTRACTOR with an awarded contract value of ₹14.69 L.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹14.69 L (11% below the estimated PAC of ₹16.50 L).