Const of Retaining Wall Behind Navjeevan School Baviskar Chawl, Bhandup (W)
Tender Specifications & Timeline
16 FieldsAward of Contract (AOC) Details
Awardee / Contractor
Anurag Enterprises
Award Date: 26-Mar-2026
Completion Period: 270 Days
Contract Financials & Scope
INR 40,848,235
Contract Award Info Updated 26-Mar-2026 12:00 PM by Nitin Dongre
Total Bidders
3
Winning Bid (L1)
₹4.08 Cr
Estimated Value (PAC)
₹4.08 Cr
Margin vs Estimate
0.00%
Completion Period
270 days
AOC Award Date
26-Mar-2026
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | Anurag Enterprises#7095864 | ₹4.08 Cr | 0.0% (L1) | 0.00% | Accepted-AOC |
| L2 | M/s. Sanatan Construction#7095933 | — | — | — | Not Admitted-Fee/PreQual/Technical |
| L2 | pranjal construction#7095888 | ₹4.17 Cr | +2.19% | Rejected-Fin | Rejected-Finance |
This education infrastructure tender covers const of Retaining Wall Behind Navjeevan School Baviskar Chawl, Bhandup (W), issued by Maharashtra Housing and Area Development Authority under reference EE/East/MSIB/e-Tender/93/ 2025-26. The estimated contract value is ₹4.08 Cr, and the tender is currently Expired. Following contract finalisation, the work has been awarded to Anurag Enterprises for a total value of ₹4.08 Cr.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in EE/EAST/MSIB. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Work order issued to L1
Not Complied with technical specification
Work order issued to L1
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
Anurag Enterprises #7095864 | 11-Dec-2025 12:02 PM | Accepted-AOC Updated: 26-Mar-2026 12:00 PM | 4,08,48,235.00 | L1 | Work order issued to L1 |
M/s. Sanatan Construction #7095933 | 11-Dec-2025 12:11 PM | Not Admitted-Fee/PreQual/Technical Updated: 03-Feb-2026 04:29 PM | — | — | Not Complied with technical specification |
pranjal construction #7095888 | 11-Dec-2025 12:06 PM | Rejected-Finance Updated: 26-Mar-2026 11:57 AM | 4,17,42,811.35 | L2 | Work order issued to L1 |
Bid Evaluation Details & Logs
technical bid opening
Date: 03-Feb-2026 04:29 PM
Officer: Nitin Dongre
Bid opening summary
technical evaluation
Date: 03-Feb-2026 04:32 PM
Officer: Nitin Dongre
finance bid opening
Date: 03-Feb-2026 04:47 PM
Officer: Nitin Dongre
Bid opening summary
finance evaluation
Date: 26-Mar-2026 11:57 AM
Officer: Nitin Dongre
About This Procurement Notice
This Maharashtra state government tender was issued by Maharashtra Housing and Area Development Authority. The estimated contract value is ₹4.08 Cr. Bids must be submitted by 15-Dec-2025 06:15 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Const of Retaining Wall Behind Navjeevan School Baviskar Chawl, Bhandup (W)"?
- The current status of this tender is "Expired". The submission deadline is 15-Dec-2025 06:15 PM. This information is sourced from official government procurement portals.
- QWho issued this Maharashtra government tender?
- This tender was issued by Maharashtra Housing and Area Development Authority. The reference number is EE/East/MSIB/e-Tender/93/ 2025-26. It is a Maharashtra state government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹4.08 Cr. This is the approximate contract value as disclosed in the official tender document.
- QWho won the contract for this tender?
- The contract for "Const of Retaining Wall Behind Navjeevan School Baviskar Chawl, Bhandup (W)" has been awarded to Anurag Enterprises with an awarded contract value of ₹4.08 Cr.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹4.08 Cr (0% above the estimated PAC of ₹4.08 Cr).