Line Quater Mohda Construction Work (Complete)
Tender Description
Line Quater Mohda Construction Work (Complete)
Tender Specifications & Timeline
16 FieldsAward of Contract (AOC) Details
Awardee / Contractor
BALAJI ENTERPRISE
Award Date: 06-Mar-2026
Completion Period: 90 Days
Contract Financials & Scope
INR 4,002,922
Contract Award Info Updated 09-Mar-2026 01:30 PM by JEETENDRA AWASE
Total Bidders
5
Total Awarded Value
₹1.73 Cr
Estimated Value (PAC)
₹48.29 L
Margin vs Estimate
-17.11%
Winning Contractors (4 - Official Awardees)
Accepted-AOCL1 to L2 Spread
+0.00%
Completion Period
90 days
AOC Award Date
06-Mar-2026
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | OM ENTERPRISES#1439066 | ₹40.03 L | 0.0% (L4) | -17.11% | Accepted-AOC |
| L2 | SHRI SHIVAY ENTERPRISES#1438845 | ₹43.29 L | 0.0% (L4) | -10.35% | Accepted-AOC |
| L3 | KRISHNA MOHAN TIWARI CONTRACTOR#1439142 | ₹44.43 L | 0.0% (L4) | -8.00% | Accepted-AOC |
| L4 | BALAJI ENTERPRISE#1438835 | ₹44.91 L | 0.0% (L4) | -7.00% | Accepted-AOC |
| L5 | D R INFRA#1436086 | — | — | — | Not Admitted-Fee/PreQual/Technical |
This tender covers line Quater Mohda Construction Work (Complete), issued by Mp Forest Department under reference MPFD_2026_48. The estimated contract value is ₹0.48 Cr, and the tender is currently Expired. Following contract finalisation, the work has been awarded to BALAJI ENTERPRISE for a total value of ₹40.03 L.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Forest Capus Mohda. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
L4
Not Complied with technical specification
L3
Lowest rate L1
L2
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
BALAJI ENTERPRISE #1438835 | 18-Feb-2026 11:23 AM | Accepted-AOC Updated: 09-Mar-2026 01:30 PM | 4491154.14 | L4 | L4 |
D R INFRA #1436086 | 14-Feb-2026 09:11 AM | Not Admitted-Fee/PreQual/Technical Updated: 24-Feb-2026 05:59 PM | — | — | Not Complied with technical specification |
KRISHNA MOHAN TIWARI CONTRACTOR #1439142 | 18-Feb-2026 04:52 PM | Accepted-AOC Updated: 09-Mar-2026 01:30 PM | 4442862.16 | L3 | L3 |
OM ENTERPRISES #1439066 | 18-Feb-2026 02:32 PM | Accepted-AOC Updated: 09-Mar-2026 01:30 PM | 4002922.22 | L1 | Lowest rate L1 |
SHRI SHIVAY ENTERPRISES #1438845 | 18-Feb-2026 11:55 AM | Accepted-AOC Updated: 09-Mar-2026 01:30 PM | 4329376.01 | L2 | L2 |
Bid Evaluation Details & Logs
technical bid opening
Date: 24-Feb-2026 05:59 PM
Officer: JEETENDRA AWASE
A total of 5 bidders participated in the tender, out of which only 1 bidder was technically unsuccessful.
technical evaluation
Date: 24-Feb-2026 06:02 PM
Officer: JEETENDRA AWASE
finance bid opening
Date: 27-Feb-2026 12:08 PM
Officer: JEETENDRA AWASE
A total of 4 bidders were selected in the financial bid, in which all the bidders were found successful in the financial bid.
finance evaluation
Date: 27-Feb-2026 12:17 PM
Officer: JEETENDRA AWASE
About This Procurement Notice
This Madhya Pradesh state government tender was issued by Mp Forest Department. The estimated contract value is ₹48.29 L. Bids must be submitted by 18-Feb-2026 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Line Quater Mohda Construction Work (Complete)"?
- The current status of this tender is "Expired". The submission deadline is 18-Feb-2026 06:00 PM. This information is sourced from official government procurement portals.
- QWho issued this Madhya Pradesh government tender?
- This tender was issued by Mp Forest Department. The reference number is MPFD_2026_48. It is a Madhya Pradesh state government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹48.29 L. This is the approximate contract value as disclosed in the official tender document.
- QWho won the contract for this tender?
- The contract for "Line Quater Mohda Construction Work (Complete)" has been awarded to BALAJI ENTERPRISE with an awarded contract value of ₹40.03 L.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹40.03 L (17.11% below the estimated PAC of ₹48.29 L).