Urgent reconstruction of collapsed and damaged portion of compound wall due to earthslide along the western side of PHE Complex Amona at Quepem.
Tender Specifications & Timeline
15 FieldsAward of Contract (AOC) Details
Awardee / Contractor
ASHISH V KARMALKAR
Award Date: 31-Mar-2026
Completion Period: 90 Days
Contract Financials & Scope
INR 964,390
AOC
Contract Award Info Updated 06-Apr-2026 01:14 PM by Harsha Kakodkar
Total Bidders
2
Winning Bid (L1)
₹9.64 L
Estimated Value (PAC)
₹12.05 L
Margin vs Estimate
-20.00%
L1 to L2 Spread
+6.25%
Completion Period
90 days
AOC Award Date
31-Mar-2026
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | ASHISH V KARMALKAR#58702 | ₹9.64 L | 0.0% (L1) | -20.00% | Accepted-AOC |
| L2 | LAXMAN S. NAIK#58703 | ₹10.25 L | +6.25% | Rejected-Fin | Rejected-Finance |
This tender covers urgent reconstruction of collapsed and damaged portion of compound wall due to earthslide along the western side of PHE Complex Amona at Quepem., issued by Department of Drinking Water under reference 48-1/DDW-WD V-ASW/2025-26/05 L4. The estimated contract value is ₹0.12 Cr, and the tender is currently Expired. Following contract finalisation, the work has been awarded to ASHISH V KARMALKAR for a total value of ₹9.64 L.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in O/o Executive Engineer, WD V, DDW, Sanguem, Goa. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Financially Accepted being 1st lowest
Financially Rejected being 2nd lowest
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
ASHISH V KARMALKAR #58702 | 20-Jan-2026 07:27 PM | Accepted-AOC Updated: 06-Apr-2026 01:14 PM | 964389.74 | L1 | Financially Accepted being 1st lowest |
LAXMAN S. NAIK #58703 | 20-Jan-2026 07:38 PM | Rejected-Finance Updated: 11-Feb-2026 12:16 PM | 1024664.09 | L2 | Financially Rejected being 2nd lowest |
Bid Evaluation Details & Logs
technical bid opening
Date: 29-Jan-2026 11:02 AM
Officer: Harsha Kakodkar
Bid opening Summary
technical evaluation
Date: 04-Feb-2026 03:51 PM
Officer: Harsha Kakodkar
finance bid opening
Date: 05-Feb-2026 11:44 AM
Officer: Harsha Kakodkar
Financial Bid opening Summary
finance evaluation
Date: 11-Feb-2026 12:16 PM
Officer: Harsha Kakodkar
About This Procurement Notice
This Goa state government tender was issued by Department of Drinking Water. The estimated contract value is ₹12.05 L. Bids must be submitted by 27-Jan-2026 03:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Urgent reconstruction of collapsed and damaged portion of compound wall due to e"?
- The current status of this tender is "Expired". The submission deadline is 27-Jan-2026 03:00 PM. This information is sourced from official government procurement portals.
- QWho issued this Goa government tender?
- This tender was issued by Department of Drinking Water. The reference number is 48-1/DDW-WD V-ASW/2025-26/05 L4. It is a Goa state government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹12.05 L. This is the approximate contract value as disclosed in the official tender document.
- QWho won the contract for this tender?
- The contract for "Urgent reconstruction of collapsed and damaged portion of compound wall due to earthslide along the western side of PHE Complex Amona at Quepem." has been awarded to ASHISH V KARMALKAR with an awarded contract value of ₹9.64 L.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹9.64 L (20% below the estimated PAC of ₹12.05 L).