STMC work for left out portion of Bhabhua Bypass(from Ch.10.80 toCh.16.00),left out portion of Chand bypass (from Ch.40.00 toCh. 40.46)and existing portion (from Ch. 40.46 toCh. 46.86) (Total Length_12.06 Km) of NH 219 under STMC work for year 25_26
Tender Specifications & Timeline
14 FieldsTotal Bidders
3
Lowest Bid (L1)
₹2.45 Cr
Estimated Value (PAC)
₹2.45 Cr
Margin vs Estimate
-0.18%
L1 to L2 Spread
+0.18%
Completion Period
365 days
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | Manish Vinod Singh Constructions#3311126 | ₹2.45 Cr | 0.0% (L1) | -0.18% | Admitted-Finance |
| L2 | ₹2.45 Cr | +0.18% | 0.00% | Admitted-Finance | |
| L3 | M/s BRIJENDRA KUMAR SINGH#3311135 | — | — | — | Not Admitted-Fee/PreQual/Technical |
This roads & highways tender covers sTMC work for left out portion of Bhabhua Bypass(from Ch.10.80 toCh.16.00),left out portion of Chand bypass (from Ch.40.00 toCh. 40.46)and existing portion (from Ch. 40.46 toCh. 46.86) (Total Length_12.06 Km) of NH 219 under STMC work for year 25_26, issued by Ministry of Road Transport and Highways under reference 02/NH/AUR/STMC/2025-26. The estimated contract value is ₹2.45 Cr, and the tender is currently Expired. Under financial bid evaluation, Manish Vinod Singh Constructions emerged as the lowest (L1) bidder with a quoted bid amount of ₹2.45 Cr.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in NH 219. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_925087.pdf
BOQ Comparative Chart
Others-Hard Copy not Submitted.
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
BALWANT CONSTRUCTIONS PRIVATE LIMITED #3311145 | 03-Nov-2025 02:53 PM | Admitted-Finance Updated: 01-Dec-2025 01:48 PM | 24514947.00 | L2 | — |
Manish Vinod Singh Constructions #3311126 | 03-Nov-2025 02:34 PM | Admitted-Finance Updated: 01-Dec-2025 01:48 PM | 24470820.10 | L1 | — |
M/s BRIJENDRA KUMAR SINGH #3311135 | 03-Nov-2025 02:40 PM | Not Admitted-Fee/PreQual/Technical Updated: 07-Nov-2025 11:51 AM | — | — | Others-Hard Copy not Submitted. |
Bid Evaluation Details & Logs
technical bid opening
Date: 07-Nov-2025 11:51 AM
Officer: Tulsi Prasad
Technical bids are opened and forwarded for evaluation.
technical evaluation
Date: 01-Dec-2025 12:51 PM
Officer: Tulsi Prasad
finance bid opening
Date: 01-Dec-2025 01:48 PM
Officer: Tulsi Prasad
Financial Bid Open and Forwarded for Financial Evaluation.
About This Procurement Notice
This central government tender was issued by Ministry of Road Transport and Highways. The estimated contract value is ₹2.45 Cr. Bids must be submitted by 03-Nov-2025 03:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "STMC work for left out portion of Bhabhua Bypass(from Ch.10.80 toCh.16.00),left"?
- The current status of this tender is "Expired". The submission deadline is 03-Nov-2025 03:00 PM. This information is sourced from official government procurement portals.
- QWho issued this central government tender?
- This tender was issued by Ministry of Road Transport and Highways. The reference number is 02/NH/AUR/STMC/2025-26. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹2.45 Cr. This is the approximate contract value as disclosed in the official tender document.
- QWho is the lowest (L1) bidder for this tender?
- Under financial bid evaluation for "STMC work for left out portion of Bhabhua Bypass(from Ch.10.80 toCh.16.00),left out portion of Chand bypass (from Ch.40.00 toCh. 40.46)and existing portion (from Ch. 40.46 toCh. 46.86) (Total Length_12.06 Km) of NH 219 under STMC work for year 25_26", Manish Vinod Singh Constructions emerged as the lowest (L1) bidder with a quoted bid amount of ₹2.45 Cr. Full bid rankings and vendor comparisons are available on BiharInfraTales.