SR to Road and culverts at Chennai Airport Chennai during the year 2023 24 SH Repairs to perimeter road in operational area Chennai Airport
Tender Description
Civil works
Tender Specifications & Timeline
13 FieldsAward of Contract (AOC) Details
Awardee / Contractor
DMW Infrastructures India Private Limited
Award Date: 15-Apr-2024
Completion Period: 90 Days
Contract Financials & Scope
INR 21,942,900
Contract Award Info Updated 15-Apr-2024 03:47 PM by SIVARAJ SARANGAPANNI
Total Bidders
6
Winning Bid (L1)
₹2.19 Cr
Estimated Value (PAC)
₹2.59 Cr
Margin vs Estimate
-15.13%
Winning Contractor (L1 - Official Awardee)
Accepted-AOCL1 to L2 Spread
+6.17%
Completion Period
90 days
AOC Award Date
15-Apr-2024
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | ₹2.19 Cr | 0.0% (L1) | -15.13% | Accepted-AOC | |
| L2 | Spancrete Civil Engineering#688432 | ₹2.33 Cr | +6.17% | Rejected-Fin | Rejected-Finance |
| L3 | RKANDSONS#689616 | ₹2.64 Cr | +20.19% | Rejected-Fin | Rejected-Finance |
| L4 | ₹3.26 Cr | +48.37% | Rejected-Fin | Rejected-Finance | |
| DQ | K.MURUGESAN#689522 | — | — | Rejected-Tech | Rejected-Technical |
| DQ | RECHI CONSTRUCTION PVT LTD#685109 | — | — | Rejected-Tech | Rejected-Technical |
This airports tender covers sR to Road and culverts at Chennai Airport Chennai during the year 2023 24 SH Repairs to perimeter road in operational area Chennai Airport, issued by Airports Authority of India under reference AAI/CHN/CMD-I/2024/003. The estimated contract value is ₹2.59 Cr, and the tender is currently Expired. Following contract finalisation, the work has been awarded to DMW Infrastructures India Private Limited for a total value of ₹2.19 Cr.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Chennai Airport. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_206795.pdf
BOQ Comparative Chart
finsummary_206795.pdf
AOC.pdf
Being L1
Being L4
Agency not fullfilled NIT condition
Agency not fullfilled NIT condition
Being L3
Being L2
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
DMW Infrastructures India Private Limited #690089 | 22-Mar-2024 05:04 PM | Accepted-AOC Updated: 15-Apr-2024 03:47 PM | 2,19,42,900.00 | L1 | Being L1 |
GURUMURTHY ENGINEERING ENTERPRISES #690200 | 22-Mar-2024 03:54 PM | Rejected-Finance Updated: 15-Apr-2024 03:40 PM | 3,25,57,650.00 | L4 | Being L4 |
K.MURUGESAN #689522 | 21-Mar-2024 08:51 AM | Rejected-Technical Updated: 30-Mar-2024 05:22 PM | — | — | Agency not fullfilled NIT condition |
RECHI CONSTRUCTION PVT LTD #685109 | 18-Mar-2024 11:53 AM | Rejected-Technical Updated: 30-Mar-2024 05:22 PM | — | — | Agency not fullfilled NIT condition |
RKANDSONS #689616 | 21-Mar-2024 06:00 PM | Rejected-Finance Updated: 15-Apr-2024 03:40 PM | 2,63,73,691.50 | L3 | Being L3 |
Spancrete Civil Engineering #688432 | 22-Mar-2024 11:35 AM | Rejected-Finance Updated: 15-Apr-2024 03:40 PM | 2,32,95,688.56 | L2 | Being L2 |
Bid Evaluation Details & Logs
technical bid opening
Date: 25-Mar-2024 11:42 AM
Officer: SIVARAJ SARANGAPANNI
All 06 Bidders admitted for Technical Evaluation
technical evaluation
Date: 30-Mar-2024 05:22 PM
Officer: SIVARAJ SARANGAPANNI
finance bid opening
Date: 15-Apr-2024 03:22 PM
Officer: SIVARAJ SARANGAPANNI
All the 04 Bidders are admitted for Financial Evaluation.
finance evaluation
Date: 15-Apr-2024 03:40 PM
Officer: SIVARAJ SARANGAPANNI
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹2.59 Cr. Bids must be submitted by 22-Mar-2024 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "SR to Road and culverts at Chennai Airport Chennai during the year 2023 24 SH Re"?
- The current status of this tender is "Expired". The submission deadline is 22-Mar-2024 06:00 PM. This information is sourced from official government procurement portals.
- QWho issued this central government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/CHN/CMD-I/2024/003. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹2.59 Cr. This is the approximate contract value as disclosed in the official tender document.
- QWho won the contract for this tender?
- The contract for "SR to Road and culverts at Chennai Airport Chennai during the year 2023 24 SH Repairs to perimeter road in operational area Chennai Airport" has been awarded to DMW Infrastructures India Private Limited with an awarded contract value of ₹2.19 Cr.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹2.19 Cr (15.13% below the estimated PAC of ₹2.59 Cr).