Balance Terminal Works Sv3k Sv4k for Singhsandra to Krishnagiri Pipe Line Under Kottanad- Banglore- Manglore Pipeline (Phase-ii)
Tender Description
BALANCE TERMINAL WORKS SV3K SV4K FOR SINGHSANDRA TO KRISHNAGIRI PIPE LINE UNDER KOCHI- KOTTANAD- BANGLORE- MANGLORE PIPELINE (PHASE-II)
Tender Specifications & Timeline
14 FieldsAward of Contract (AOC) Details
Awardee / Contractor
RAJ CONSTRUCTION
Award Date: 04-Sep-2024
Completion Period: 210 Days
Contract Financials & Scope
INR 130,206,503.6
Contract Award Info Updated 04-Sep-2024 11:06 AM by RAKESH SHARMA
Total Bidders
1
Winning Bid (L1)
₹13.02 Cr
Estimated Value (PAC)
—
Margin vs Estimate
—
Completion Period
210 days
AOC Award Date
04-Sep-2024
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | RAJ CONSTRUCTION#687217 | ₹13.02 Cr | 0.0% (L1) | — | Accepted-AOC |
This oil & gas tender covers balance Terminal Works Sv3k Sv4k for Singhsandra to Krishnagiri Pipe Line Under Kottanad- Banglore- Manglore Pipeline (Phase-ii), issued by Gail India Limited under reference 05/51/23RQ/GAIL/001(i)-14. This work is part of the development of Noida Water Supply — government tender titles use official department terminology rather than the common name. The tender is currently Expired. Following contract finalisation, the work was awarded to RAJ CONSTRUCTION for a total value of ₹13.02 Cr.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Noida. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_198100.pdf
BOQ Comparative Chart
finsummary_198100.pdf
FOAraj.pdf
Awarded, L1 Bidder
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
RAJ CONSTRUCTION #687217 | 16-Mar-2024 11:36 AM | Accepted-AOC Updated: 04-Sep-2024 11:06 AM | 13,02,06,503.60 | L1 | Awarded, L1 Bidder |
Bid Evaluation Details & Logs
technical bid opening
Date: 18-Mar-2024 03:23 PM
Officer: RAKESH SHARMA
Technical Bid Opening
technical evaluation
Date: 04-Jun-2024 10:15 AM
Officer: RAKESH SHARMA
finance bid opening
Date: 04-Jun-2024 03:28 PM
Officer: RAKESH SHARMA
Price Bid Opening
finance evaluation
Date: 04-Sep-2026 12:01 AM
Officer: RAKESH SHARMA
About This Procurement Notice
This central government tender was issued by Gail India Limited. Bids must be submitted by 16-Mar-2024 02:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Balance Terminal Works Sv3k Sv4k for Singhsandra to Krishnagiri Pipe Line Under "?
- The current status of this tender is "Expired". The submission deadline is 16-Mar-2024 02:00 PM. This information is sourced from official government procurement portals.
- QWho issued this central government tender?
- This tender was issued by Gail India Limited. The reference number is 05/51/23RQ/GAIL/001(i)-14. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value has not been disclosed for this procurement notice. Please refer to the official tender documents for detailed specifications.
- QIs this the Noida Water Supply tender?
- Yes — "Balance Terminal Works Sv3k Sv4k for Singhsandra to Krishnagiri Pipe Line Under Kottanad- Banglore- Manglore Pipeline (Phase-ii)" is the official government tender title covering Noida Water Supply development works. Government tender titles for this sector use official department terminology rather than the site's common name.
- QWho won the contract for this tender?
- The contract for "Balance Terminal Works Sv3k Sv4k for Singhsandra to Krishnagiri Pipe Line Under Kottanad- Banglore- Manglore Pipeline (Phase-ii)" was awarded to RAJ CONSTRUCTION with an awarded contract value of ₹13.02 Cr.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹13.02 Cr.