Completion of balance works and obtaining statutory approvals of 30KWp rooftop solar power plant at AAI residential Colony.
Tender Details
Financial & Timeline
Award of Contract (AOC) Details
Awardee / Contractor
Skysolars/kavinkumar
Award Date: 03-Dec-2023
Completion Period: 90 Days
Contract Financials & Scope
INR 745,000
Contract Award Info Updated 26-Mar-2024 05:09 PM by KASI R
This airports tender covers completion of balance works and obtaining statutory approvals of 30KWp rooftop solar power plant at AAI residential Colony., issued by Airports Authority of India under reference AAI/CBIA/E-E/30 KWP SOLAR/23-24. The estimated contract value is ₹0.09 Cr, and The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Coimbatore International Airport. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents & Downloads
technical_185931.pdf
Key: 2023_AAI_167039_1/technical_185931.pdf
techsummary_185931.pdf
Key: 2023_AAI_167039_1/techsummary_185931.pdf
finance_185931.pdf
Key: 2023_AAI_167039_1/finance_185931.pdf
BOQ Comparative Chart
Key: 2023_AAI_167039_1/BOQ Comparative Chart.xlsx
finsummary_185931.pdf
Key: 2023_AAI_167039_1/finsummary_185931.pdf
WORKORDER.pdf
Key: 2023_AAI_167039_1/WORKORDER.pdf
Submitted Bids & Bidder Details
Being L2
Being L1
| Bid No. / Bidder | Submitted On | Status | Fin. Value | Fin. Rank | Remarks / Logs |
|---|---|---|---|---|---|
Naturetech Infrastruture Pvt. Ltd. #625641 | 25-Oct-2023 05:43 PM | Rejected-Finance Updated: 16-Nov-2023 12:55 PM | 7,72,000.00 | LL2 | Being L2 |
Skysolars/kavinkumar #624510 | 25-Oct-2023 12:42 PM | Accepted-AOC Updated: 26-Mar-2024 05:10 PM | 7,45,000.00 | LL1 | Being L1 |
Bid Evaluation Details & Logs
technical bid opening
Date: 08-Nov-2023 11:52 AM
Officer: KASI R
Bids are admitted for Technical Evaluation
technical evaluation
Date: 16-Nov-2023 12:28 PM
Officer: KASI R
finance bid opening
Date: 16-Nov-2023 12:40 PM
Officer: KASI R
Bids are admitted for Financial Evaluation.
finance evaluation
Date: 16-Nov-2023 12:55 PM
Officer: KASI R
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹8.86 L. Bids must be submitted by 01-Nov-2023 05:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- What is the status of the tender "Completion of balance works and obtaining statutory approvals of 30KWp rooftop s"?
- The current status of this tender is "Expired". The submission deadline is 01-Nov-2023 05:00 PM. This information is sourced from official government procurement portals.
- Who issued this Bihar government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/CBIA/E-E/30 KWP SOLAR/23-24. It is a central government procurement notice.
- What is the estimated value of this tender?
- The estimated tender value is ₹8.86 L. This is the approximate contract value as disclosed in the official tender document.