Construction of Boundary Wall around Phase-3 at Ayodhya Airport Ayodhya
Tender Details
Financial & Timeline
Award of Contract (AOC) Details
Awardee / Contractor
M/s Raja Infraconstruction Pvt Ltd
Award Date: 21-Aug-2023
Completion Period: 300 Days
Contract Financials & Scope
INR 69,852,450
Work order
Contract Award Info Updated 13-Sep-2023 12:29 PM by RAJENDRA PRASAD MEENA
This airports tender covers construction of Boundary Wall around Phase-3 at Ayodhya Airport Ayodhya, issued by Airports Authority of India under reference AAI/AYD/Jt.GM (P)/P-3 BW/2023-24. The estimated contract value is ₹11.46 Cr, and The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Ayodhya Airport. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents & Downloads
techsummary_170407.pdf
Key: 2023_AAI_155224_1/techsummary_170407.pdf
finance_170407.pdf
Key: 2023_AAI_155224_1/finance_170407.pdf
BOQ Comparative Chart
Key: 2023_AAI_155224_1/BOQ Comparative Chart.xlsx
finsummary_170407.pdf
Key: 2023_AAI_155224_1/finsummary_170407.pdf
WO.pdf
Key: 2023_AAI_155224_1/WO.pdf
Submitted Bids & Bidder Details
Not L1 bidder
Not L1 bidder
Not L1 bidder
Agency was asked to furnish the Form -D as per NIT format but the agency have not submitted. However Bid capacity workout on the basis of available information in the application. Which does not meets the NIT criteria so that agency disqualified.
L1 bidder
Not L1 bidder
Not L1 bidder
Not L1 bidder
Not L1 bidder
Agency was asked to furnish the completion certificate but agency have not submitted any documents under shortfall folder through CPP portal. Therefore disqualified.
Not L1 bidder
Not L1 bidder
Not L1 bidder
| Bid No. / Bidder | Submitted On | Status | Fin. Value | Fin. Rank | Remarks / Logs |
|---|---|---|---|---|---|
Durga Construction #567855 | 27-Jun-2023 03:52 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 10,05,41,645.00 | LL-9 | Not L1 bidder |
GOYAL IRON AND STEEL TRADERS #571211 | 28-Jun-2023 05:36 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 8,13,30,655.00 | LL-2 | Not L1 bidder |
K.D.CONSTRUCTION #567559 | 28-Jun-2023 05:19 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 8,36,18,997.00 | LL-4 | Not L1 bidder |
METAL ENGINEERING #565873 | 21-Jun-2026 07:11 PM | Rejected-Technical Updated: 02-Aug-2023 12:18 PM | — | — | Agency was asked to furnish the Form -D as per NIT format but the agency have not submitted. However Bid capacity workout on the basis of available information in the application. Which does not meets the NIT criteria so that agency disqualified. |
M/s Raja Infraconstruction Pvt Ltd #565870 | 21-Jun-2023 02:19 PM | Accepted-AOC Updated: 13-Sep-2023 12:30 PM | 6,98,52,450.00 | LL-1 | L1 bidder |
M/S SARADA CONSTRUCTION #565586 | 21-Jun-2023 01:29 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 8,15,60,140.00 | LL-3 | Not L1 bidder |
M/S VEE KAY CONSTRUCTIONS #567821 | 28-Jun-2023 04:12 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 9,47,94,572.00 | LL-6 | Not L1 bidder |
Neeraj Constructions #567005 | 20-Jun-2023 06:51 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 10,48,54,765.00 | LL-11 | Not L1 bidder |
NIRMAN #571466 | 28-Jun-2023 04:41 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 9,70,70,700.00 | LL-7 | Not L1 bidder |
sanjeev kumar contractors private limited #567675 | 21-Jun-2023 02:18 PM | Rejected-Technical Updated: 02-Aug-2023 12:18 PM | — | — | Agency was asked to furnish the completion certificate but agency have not submitted any documents under shortfall folder through CPP portal. Therefore disqualified. |
SHIVA BUILDTECH PVT LTD #567354 | 21-Jun-2023 01:21 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 8,51,03,320.60 | LL-5 | Not L1 bidder |
Tripatra India Private Limited #565505 | 28-Jun-2023 03:12 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 10,33,65,310.00 | LL-10 | Not L1 bidder |
vss buildcon pvt ltd #562674 | 28-Jun-2023 04:31 PM | Rejected-Finance Updated: 14-Aug-2023 02:05 PM | 9,89,79,850.00 | LL-8 | Not L1 bidder |
Bid Evaluation Details & Logs
technical bid opening
Date: 06-Jul-2023 02:38 PM
Officer: RAJENDRA PRASAD MEENA
Technical bid successfully opened.
technical evaluation
Date: 02-Aug-2023 12:18 PM
Officer: RAJENDRA PRASAD MEENA
finance bid opening
Date: 02-Aug-2023 04:54 PM
Officer: RAJENDRA PRASAD MEENA
Financial bid opened successfully.
finance evaluation
Date: 14-Aug-2023 02:05 PM
Officer: RAJENDRA PRASAD MEENA
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹11.46 Cr. Bids must be submitted by 28-Jun-2023 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- What is the status of the tender "Construction of Boundary Wall around Phase-3 at Ayodhya Airport Ayodhya"?
- The current status of this tender is "Expired". The submission deadline is 28-Jun-2023 06:00 PM. This information is sourced from official government procurement portals.
- Who issued this Bihar government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/AYD/Jt.GM (P)/P-3 BW/2023-24. It is a central government procurement notice.
- What is the estimated value of this tender?
- The estimated tender value is ₹11.46 Cr. This is the approximate contract value as disclosed in the official tender document.