Replacement of Baggage Handling System at Lilabari Airport
Tender Specifications & Timeline
13 FieldsAward of Contract (AOC) Details
Awardee / Contractor
GANNON DUNKERLEY AND CO LTD
Award Date: 17-Aug-2023
Completion Period: 120 Days
Contract Financials & Scope
INR 5,748,000
Work awarded to M/s Gannon Dunkerley & Co Ltd
Contract Award Info Updated 27-May-2024 05:36 PM by Naveen Kumar Marwaha
Total Bidders
4
Winning Bid (L1)
₹56.13 L
Estimated Value (PAC)
₹74.35 L
Margin vs Estimate
-22.69%
L1 to L2 Spread
+65.49%
Completion Period
120 days
AOC Award Date
17-Aug-2023
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | GANNON DUNKERLEY AND CO LTD#551637 | ₹56.13 L | 0.0% (L1) | -24.51% | Accepted-AOC |
| L2 | ₹95.12 L | +65.49% | Rejected-Fin | Rejected-Finance | |
| L3 | ₹98.91 L | +72.08% | Rejected-Fin | Rejected-Finance | |
| DQ | — | — | Rejected-Tech | Rejected-Technical |
This airports tender covers replacement of Baggage Handling System at Lilabari Airport, issued by Airports Authority of India under reference AAI/LBR/AGM(EE)/BHS/CW01/23-24. The estimated contract value is ₹0.74 Cr, and the tender is currently Expired. Following contract finalisation, the work was awarded to GANNON DUNKERLEY AND CO LTD for a total value of ₹57.48 L.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in AAI, Lilabari Airport. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_166344.pdf
BOQ Comparative Chart
finsummary_166344.pdf
AwardLetterBHS.pdf
L2
Not meeting PQ criteria.
Being L1 bidder
L3
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
DElite System Engineering (India) Pvt. Ltd. #550813 | 10-May-2023 01:54 PM | Rejected-Finance Updated: 17-Aug-2023 01:07 PM | 95,12,172.11 | L2 | L2 |
Fox Solutions Private Limited #547431 | 10-May-2023 04:52 PM | Rejected-Technical Updated: 22-May-2023 10:21 AM | — | — | Not meeting PQ criteria. |
GANNON DUNKERLEY AND CO LTD #551637 | 08-May-2023 06:26 PM | Accepted-AOC Updated: 27-May-2024 05:37 PM | 56,13,053.00 | L1 | Being L1 bidder |
PREMIER ENGINEERING TECHNICS PVT. LTD. #551697 | 10-May-2023 11:36 AM | Rejected-Finance Updated: 17-Aug-2023 01:07 PM | 98,91,215.40 | L3 | L3 |
Bid Evaluation Details & Logs
technical bid opening
Date: 15-May-2023 04:09 PM
Officer: Naveen Kumar Marwaha
Technical Bid (Envelope-1) opened.
technical evaluation
Date: 22-May-2023 10:21 AM
Officer: Naveen Kumar Marwaha
finance bid opening
Date: 16-Aug-2023 10:16 AM
Officer: Naveen Kumar Marwaha
Financial Bid opened, M/s. GANNON DUNKERLEY AND CO LTD. is L1 bidder
finance evaluation
Date: 17-Aug-2023 01:07 PM
Officer: Naveen Kumar Marwaha
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹74.35 L. Bids must be submitted by 10-May-2023 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Replacement of Baggage Handling System at Lilabari Airport"?
- The current status of this tender is "Expired". The submission deadline is 10-May-2023 06:00 PM. This information is sourced from official government procurement portals.
- QWho issued this central government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/LBR/AGM(EE)/BHS/CW01/23-24. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹74.35 L. This is the approximate contract value as disclosed in the official tender document.
- QWho won the contract for this tender?
- The contract for "Replacement of Baggage Handling System at Lilabari Airport" was awarded to GANNON DUNKERLEY AND CO LTD with an awarded contract value of ₹57.48 L.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹57.48 L (22.69% below the estimated PAC of ₹74.35 L).