ARMO OF E and M Installations at DVOR, Kanchipuram for the year 2022-24 -Two years. SH AMC of E and M Installations at DVOR, Kanchipuram
Tender Specifications & Timeline
13 FieldsAward of Contract (AOC) Details
Awardee / Contractor
LAKSHMI ELECTRICAL ENTERPRISES
Award Date: 07-Feb-2022
Completion Period: 730 Days
Contract Financials & Scope
INR 2,598,288
Contract Award Info Updated 04-Feb-2022 05:52 PM by SUJATHA R
Total Bidders
9
Winning Bid (L1)
₹25.98 L
Estimated Value (PAC)
₹33.56 L
Margin vs Estimate
-22.57%
L1 to L2 Spread
+6.69%
Completion Period
730 days
AOC Award Date
07-Feb-2022
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | ₹25.98 L | 0.0% (L1) | -22.57% | Accepted-AOC | |
| L2 | ₹27.72 L | +6.69% | Rejected-Fin | Rejected-Finance | |
| L3 | ₹27.89 L | +7.35% | Rejected-Fin | Rejected-Finance | |
| L4 | CENTRE TAP ENGINEERING#374909 | ₹28.80 L | +10.84% | Rejected-Fin | Rejected-Finance |
| L5 | M K ENTERPRISES#378590 | ₹29.52 L | +13.61% | Rejected-Fin | Rejected-Finance |
| L6 | ₹30.25 L | +16.40% | Rejected-Fin | Rejected-Finance | |
| L7 | CHENNAI ENGINEERING SERVICES#376461 | ₹30.44 L | +17.17% | Rejected-Fin | Rejected-Finance |
| L8 | ₹30.76 L | +18.40% | Rejected-Fin | Rejected-Finance | |
| L9 | ₹31.80 L | +22.39% | Rejected-Fin | Rejected-Finance |
This airports tender covers aRMO OF E and M Installations at DVOR, Kanchipuram for the year 2022-24 -Two years. SH AMC of E and M Installations at DVOR, Kanchipuram, issued by Airports Authority of India under reference AAI/RHQ-SR/AGM(E-E)/AMC-KPM/. This work is part of the development of Chennai airport Airport — government tender titles use official department terminology rather than the common name. The estimated contract value is ₹0.34 Cr, and the tender is currently Expired. Following contract finalisation, the work was awarded to LAKSHMI ELECTRICAL ENTERPRISES for a total value of ₹25.98 L.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Chennai airport. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_109366.pdf
BOQ Comparative Chart
finsummary_109366.pdf
AOC.pdf
L8
L4
L7
L2
L1
L5
L9
L6
L3
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
ABHISHEK INTEGRATIONS LIMITED #378213 | 24-Jan-2022 09:43 PM | Rejected-Finance Updated: 04-Feb-2022 05:51 PM | 30,76,416.00 | L8 | L8 |
CENTRE TAP ENGINEERING #374909 | 19-Jan-2022 12:42 PM | Rejected-Finance Updated: 04-Feb-2022 05:51 PM | 28,80,000.00 | L4 | L4 |
CHENNAI ENGINEERING SERVICES #376461 | 24-Jan-2022 04:55 PM | Rejected-Finance Updated: 04-Feb-2022 05:51 PM | 30,44,328.00 | L7 | L7 |
DElite System Engineering (India) Pvt. Ltd. #376180 | 24-Jan-2022 04:36 PM | Rejected-Finance Updated: 04-Feb-2022 05:51 PM | 27,72,232.32 | L2 | L2 |
LAKSHMI ELECTRICAL ENTERPRISES #374648 | 24-Jan-2022 02:38 PM | Accepted-AOC Updated: 04-Feb-2022 05:52 PM | 25,98,288.00 | L1 | L1 |
M K ENTERPRISES #378590 | 25-Jan-2022 05:42 PM | Rejected-Finance Updated: 04-Feb-2022 05:51 PM | 29,52,000.00 | L5 | L5 |
PREMIER ENGINEERING TECHNICS PVT. LTD. #377135 | 22-Jan-2022 04:25 PM | Rejected-Finance Updated: 04-Feb-2022 05:51 PM | 31,79,976.00 | L9 | L9 |
SHRADDHA ENGINEERING AND FACILITY SERVICES #370891 | 25-Jan-2022 10:14 AM | Rejected-Finance Updated: 04-Feb-2022 05:51 PM | 30,24,528.00 | L6 | L6 |
TOOT MNE TECH PRIVATE LIMITED #376373 | 24-Jan-2022 04:33 PM | Rejected-Finance Updated: 04-Feb-2022 05:51 PM | 27,89,208.00 | L3 | L3 |
Bid Evaluation Details & Logs
technical bid opening
Date: 28-Jan-2022 05:29 PM
Officer: SUJATHA R
Cover - I opened and taken for scrutiny
technical evaluation
Date: 01-Feb-2022 11:17 AM
Officer: SUJATHA R
finance bid opening
Date: 04-Feb-2022 05:42 PM
Officer: SUJATHA R
Cover-II opened and taken for scrutiny
finance evaluation
Date: 04-Feb-2022 05:51 PM
Officer: SUJATHA R
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹33.56 L. Bids must be submitted by 25-Jan-2022 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "ARMO OF E and M Installations at DVOR, Kanchipuram for the year 2022-24 -Two yea"?
- The current status of this tender is "Expired". The submission deadline is 25-Jan-2022 06:00 PM. This information is sourced from official government procurement portals.
- QWho issued this central government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/RHQ-SR/AGM(E-E)/AMC-KPM/. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹33.56 L. This is the approximate contract value as disclosed in the official tender document.
- QIs this the Chennai airport Airport tender?
- Yes — "ARMO OF E and M Installations at DVOR, Kanchipuram for the year 2022-24 -Two years. SH AMC of E and M Installations at DVOR, Kanchipuram" is the official government tender title covering Chennai airport Airport development works. Government tender titles for this sector use official department terminology rather than the site's common name.
- QWho won the contract for this tender?
- The contract for "ARMO OF E and M Installations at DVOR, Kanchipuram for the year 2022-24 -Two years. SH AMC of E and M Installations at DVOR, Kanchipuram" was awarded to LAKSHMI ELECTRICAL ENTERPRISES with an awarded contract value of ₹25.98 L.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹25.98 L (22.57% below the estimated PAC of ₹33.56 L).