Construction of Elevated Corridor in Ranchi city from km 0.00 to km 3.570 of NH75 including down ramp on NH23 from km 0.000 to km 0.610 in the State of Jharkhand on EPC mode
Tender Details
Financial & Timeline
This roads & highways tender covers construction of Elevated Corridor in Ranchi city from km 0.00 to km 3.570 of NH75 including down ramp on NH23 from km 0.000 to km 0.610 in the State of Jharkhand on EPC mode, issued by National Highways Authority of India under reference NHAI/11012/JH/ Ele.Corr.Ranchi/2021. The estimated contract value is ₹430.71 Cr, and The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in NHAI HQ. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
technical_106224.pdf
techsummary_106224.pdf
finance_106224.pdf
Submitted Bids & Bidder Details
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
Dineshchandra R Agrawal Infracon Pvt. Ltd. #398709 | 09-Mar-2022 10:33 AM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
EVRASCON-TLL JV #392934 | 09-Mar-2022 09:19 AM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
ITD Cementation India Limited #367652 | 09-Mar-2022 09:40 AM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
KCC Buildcon Private Limited #398718 | 09-Mar-2022 10:37 AM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
L&T GEOSTRUCTURE PRIVATE LIMITED #398698 | 08-Mar-2022 07:15 PM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
M G Contractors Pvt Ltd #384415 | 08-Mar-2022 05:37 PM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
RAJBIR CONSTRUCTION PVT LTD #398788 | 08-Mar-2022 09:43 PM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
RAM KRIPAL SINGH CONSTRUCTION PRIVATE LIMITED #398763 | 09-Mar-2022 09:33 AM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
RKD CONSTRUCTION PVT.LTD #384850 | 09-Mar-2022 10:32 AM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
Royal Infraconstru Limited #398795 | 09-Mar-2022 10:01 AM | Admitted-Finance Updated: 28-Mar-2022 04:23 PM | — | — | — |
Bid Evaluation Details & Logs
technical bid opening
Date: 24-Mar-2022 07:25 PM
Officer: AJAY GUPTA
TECHNICAL EVALUATION RESULT
technical evaluation
Date: 28-Mar-2022 04:12 PM
Officer: AJAY GUPTA
finance bid opening
Date: 28-Mar-2022 04:23 PM
Officer: AWADHESH KUMAR
BIDS OPENED
About This Procurement Notice
This central government tender was issued by National Highways Authority of India. The estimated contract value is ₹430.71 Cr. Bids must be submitted by 09-Mar-2022 11:00 AM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- What is the status of the tender "Construction of Elevated Corridor in Ranchi city from km 0.00 to km 3.570 of NH7"?
- The current status of this tender is "Expired". The submission deadline is 09-Mar-2022 11:00 AM. This information is sourced from official government procurement portals.
- Who issued this Bihar government tender?
- This tender was issued by National Highways Authority of India. The reference number is NHAI/11012/JH/ Ele.Corr.Ranchi/2021. It is a central government procurement notice.
- What is the estimated value of this tender?
- The estimated tender value is ₹430.71 Cr. This is the approximate contract value as disclosed in the official tender document.