Construction of Strom Water drain at New Airport Colony Mumbai.
Tender Details
Financial & Timeline
Award of Contract (AOC) Details
Awardee / Contractor
Vinayak Infra Signs and Projects Pvt Ltd
Award Date: 22-Apr-2022
Completion Period: 240 Days
Contract Financials & Scope
INR 9,536,910
Contract Award Info Updated 22-Apr-2022 04:18 PM by Jaipal Badge
This airports tender covers construction of Strom Water drain at New Airport Colony Mumbai., issued by Airports Authority of India under reference AAI/MUM/NAC/E-C/21-22/Drain/. The estimated contract value is ₹1.59 Cr, and The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Mumbai. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents & Downloads
techsummary_107120.pdf
Key: 2021_AAI_98074_1/techsummary_107120.pdf
finance_107120.pdf
Key: 2021_AAI_98074_1/finance_107120.pdf
BOQ Comparative Chart
Key: 2021_AAI_98074_1/BOQ Comparative Chart.xlsx
finsummary_107120.pdf
Key: 2021_AAI_98074_1/finsummary_107120.pdf
BOQsummarydrainwork.pdf
Key: 2021_AAI_98074_1/BOQsummarydrainwork.pdf
Submitted Bids & Bidder Details
L15
L7
L20
L10
L12
L19
Rejected Subseqent to technical evalavation
L11
L13
L3
L2
L5
L8
L14
Work awarded
L18
L12
L16
L9
L6
L21
L17
L4
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
Aavkar Corporation #365325 | 24-Dec-2021 05:21 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,28,60,305.20 | L15 | L15 |
Anshu Aman Construction and Services Pvt. Ltd. #365539 | 25-Dec-2021 02:36 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,19,44,840.00 | L7 | L7 |
arcoma #364774 | 25-Dec-2021 03:10 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,43,66,535.00 | L20 | L20 |
Baltej Infra LLP #365594 | 25-Dec-2021 05:26 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,22,38,912.00 | L10 | L10 |
Classion Projects (I) Pvt. Ltd. #364798 | 25-Dec-2021 01:11 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,23,41,708.00 | L12 | L12 |
D B Infratech #364022 | 25-Dec-2021 03:32 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,42,80,195.00 | L19 | L19 |
JAIN AGENCIES #365485 | 25-Dec-2021 03:44 PM | Rejected-Technical Updated: 01-Feb-2022 01:00 PM | — | — | Rejected Subseqent to technical evalavation |
K N RAI #362500 | 24-Dec-2021 04:12 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,22,84,380.00 | L11 | L11 |
M I CONSTRUCTIONS #365418 | 25-Dec-2021 02:49 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,25,61,935.00 | L13 | L13 |
M K CONSTRUCTION #365429 | 25-Dec-2021 12:08 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,10,51,231.00 | L3 | L3 |
M/S SANJAY KUMAR #364479 | 25-Dec-2021 01:56 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,07,96,716.69 | L2 | L2 |
M/s. VARUN CONSTRUCTIONS #365272 | 25-Dec-2021 02:41 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,15,89,706.80 | L5 | L5 |
Nilkanth Construction. #364406 | 25-Dec-2021 02:35 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,19,95,045.00 | L8 | L8 |
Noble Construction Company #365427 | 25-Dec-2021 02:08 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,28,18,655.00 | L14 | L14 |
Om Sai Associates #364091 | 23-Dec-2021 10:41 PM | Accepted-AOC Updated: 22-Apr-2022 04:18 PM | 95,36,910.00 | L1 | Work awarded |
PIYUSH ENTERPRISES #364767 | 23-Dec-2021 05:45 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,37,24,890.00 | L18 | L18 |
P.R.Patil #365352 | 25-Dec-2021 05:57 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,53,18,070.75 | L12 | L12 |
RECHI CONSTRUCTION PVT LTD #364586 | 22-Dec-2021 11:38 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,31,74,140.00 | L16 | L16 |
Shreejikrupa Project Limited #364441 | 25-Dec-2021 10:18 AM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,22,35,200.00 | L9 | L9 |
Shrikrishna Construction #364408 | 23-Dec-2021 08:07 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,19,14,530.00 | L6 | L6 |
S.K. CONSTRUCTION #365588 | 25-Dec-2021 05:07 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,43,99,775.00 | L21 | L21 |
SRS Infra Projects Pvt Ltd #365535 | 25-Dec-2021 05:42 PM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,34,02,700.00 | L17 | L17 |
Vinayak Infra Signs and Projects Pvt Ltd #364278 | 25-Dec-2021 11:55 AM | Rejected-AOC Updated: 22-Apr-2022 04:18 PM | 1,14,98,025.00 | L4 | L4 |
Bid Evaluation Details & Logs
technical bid opening
Date: 17-Jan-2022 04:52 PM
Officer: Jaipal Badge
Provisionally accepted the bid of those bidders who have requested to submit the required document in Short fall Documents folder.
technical evaluation
Date: 01-Feb-2022 01:00 PM
Officer: Jaipal Badge
finance bid opening
Date: 01-Feb-2022 05:38 PM
Officer: Jaipal Badge
The finance bid of eligible bidders has been opened and a comparative statement prepared accordingly.
finance evaluation
Date: 20-Apr-2022 03:06 PM
Officer: Jaipal Badge
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹1.59 Cr. Bids must be submitted by 25-Dec-2021 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- What is the status of the tender "Construction of Strom Water drain at New Airport Colony Mumbai."?
- The current status of this tender is "Expired". The submission deadline is 25-Dec-2021 06:00 PM. This information is sourced from official government procurement portals.
- Who issued this Bihar government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/MUM/NAC/E-C/21-22/Drain/. It is a central government procurement notice.
- What is the estimated value of this tender?
- The estimated tender value is ₹1.59 Cr. This is the approximate contract value as disclosed in the official tender document.