Construction of 4 lane Access Controlled New Greenfield Highway Section of NH-365BG Khammam-Devarapalle of length 29.462 km Design Chainage 132.664 to 162.126 under Inter Corridor Route under BMP on HAM in the state of Andhra Pradesh.
Tender Specifications & Timeline
13 FieldsAward of Contract (AOC) Details
Awardee / Contractor
BEKEM INFRA PROJECTS PVT. LTD.
Award Date: 19-Oct-2022
Completion Period: 730 Days
Contract Financials & Scope
INR 6,088,300,000
Contract Award Info Updated 19-Oct-2022 04:12 PM by PRABHAT RANJAN
Total Bidders
11
Winning Bid (L1)
₹608.83 Cr
Estimated Value (PAC)
₹527.42 Cr
Margin vs Estimate
+15.44%
L1 to L2 Spread
+3.88%
Completion Period
730 days
AOC Award Date
19-Oct-2022
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | ₹608.83 Cr | 0.0% (L1) | +15.44% | Accepted-AOC | |
| L2 | KMV Projects Limited#210324 | ₹632.48 Cr | +3.88% | Rejected | Rejected-AOC |
| L3 | ₹651.77 Cr | +7.05% | Rejected | Rejected-AOC | |
| L4 | KPC PROJECTS LIMITED#207360 | ₹658.72 Cr | +8.19% | Rejected | Rejected-AOC |
| L5 | ₹682.71 Cr | +12.13% | Rejected | Rejected-AOC | |
| L6 | ₹700.91 Cr | +15.12% | Rejected | Rejected-AOC | |
| L7 | ₹705.17 Cr | +15.82% | Rejected | Rejected-AOC | |
| L8 | Adani Road Transport Limited#232160 | ₹707.23 Cr | +16.16% | Rejected | Rejected-AOC |
| L9 | BVSR CONSTRUCTIONS PVT LTD#232258 | ₹757.23 Cr | +24.37% | Rejected | Rejected-AOC |
| L10 | ₹818.62 Cr | +34.46% | Rejected | Rejected-AOC | |
| DQ | — | — | Rejected-Tech | Rejected-Technical |
This roads & highways tender covers construction of 4 lane Access Controlled New Greenfield Highway Section of NH-365BG Khammam-Devarapalle of length 29.462 km Design Chainage 132.664 to 162.126 under Inter Corridor Route under BMP on HAM in the state of Andhra Pradesh., issued by National Highways Authority of India under reference NHAI/Tech/AP/Khm-Dvr /Pkg-V/2018-19. The estimated contract value is ₹527.42 Cr, and the tender is currently Expired. Following contract finalisation, the work was awarded to BEKEM INFRA PROJECTS PVT. LTD. for a total value of ₹608.83 Cr.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in NHAI HQ. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
technical_60971.pdf
techsummary_60971.pdf
finance_60971.pdf
finsummary_60971.pdf
1058LOAPkgV.pdf
RESPONSIVE
RESPONSIVE
RESPONSIVE
RESPONSIVE
RESPONSIVE
RESPONSIVE
RESPONSIVE
RESPONSIVE
RESPONSIVE
TECHNICALLY NON RESPONSIVE
RESPONSIVE
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
Adani Road Transport Limited #232160 | 07-Jan-2021 10:10 AM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 7,07,23,00,000.00 | L8 | RESPONSIVE |
BEKEM INFRA PROJECTS PVT. LTD. #232185 | 07-Jan-2021 04:03 AM | Accepted-AOC Updated: 19-Oct-2022 04:13 PM | 6,08,83,00,000.00 | L1 | RESPONSIVE |
BVSR CONSTRUCTIONS PVT LTD #232258 | 07-Jan-2021 10:52 AM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 7,57,23,00,000.00 | L9 | RESPONSIVE |
D P JAIN AND COMPANY INFRASTRUCTURE PRIVATE LIMITED #232270 | 07-Jan-2021 10:32 AM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 6,82,71,00,000.00 | L5 | RESPONSIVE |
IRB Infrastructure Developers Limited #232248 | 07-Jan-2021 10:38 AM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 8,18,62,00,000.00 | L10 | RESPONSIVE |
KMV Projects Limited #210324 | 07-Jan-2021 10:54 AM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 6,32,48,00,000.00 | L2 | RESPONSIVE |
KPC PROJECTS LIMITED #207360 | 07-Jan-2021 10:09 AM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 6,58,72,00,000.00 | L4 | RESPONSIVE |
MEGHA ENGINEERING AND INFRASTRUCTURES LIMITED #231550 | 07-Jan-2021 10:29 AM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 6,51,77,00,000.00 | L3 | RESPONSIVE |
M/s NSPR Constructions India Private Limited #232078 | 07-Jan-2021 10:25 AM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 7,00,91,00,000.00 | L6 | RESPONSIVE |
Oriental Structural Engineers Pvt. Ltd. #232093 | 06-Jan-2021 05:18 PM | Rejected-Technical Updated: 26-Feb-2021 11:43 AM | — | — | TECHNICALLY NON RESPONSIVE |
PSK INFRASTRUCTURES AND PROJECTS PRIVATE LIMITED #218897 | 06-Jan-2021 06:19 PM | Rejected-AOC Updated: 19-Oct-2022 04:13 PM | 7,05,17,00,000.00 | L7 | RESPONSIVE |
Bid Evaluation Details & Logs
technical bid opening
Date: 08-Feb-2021 04:26 PM
Officer: DINESH SHERAWAT
TECHNICAL EVALUATION RESULT
technical evaluation
Date: 26-Feb-2021 11:43 AM
Officer: NAVIN KUMAR CHAURASIA
finance bid opening
Date: 26-Feb-2021 11:59 AM
Officer: DINESH SHERAWAT
BIDS OPENED
finance evaluation
Date: 19-Oct-2022 04:11 PM
Officer: PRABHAT RANJAN
About This Procurement Notice
This central government tender was issued by National Highways Authority of India. The estimated contract value is ₹527.42 Cr. Bids must be submitted by 07-Jan-2021 11:00 AM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Construction of 4 lane Access Controlled New Greenfield Highway Section of NH-36"?
- The current status of this tender is "Expired". The submission deadline is 07-Jan-2021 11:00 AM. This information is sourced from official government procurement portals.
- QWho issued this central government tender?
- This tender was issued by National Highways Authority of India. The reference number is NHAI/Tech/AP/Khm-Dvr /Pkg-V/2018-19. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹527.42 Cr. This is the approximate contract value as disclosed in the official tender document.
- QWho won the contract for this tender?
- The contract for "Construction of 4 lane Access Controlled New Greenfield Highway Section of NH-365BG Khammam-Devarapalle of length 29.462 km Design Chainage 132.664 to 162.126 under Inter Corridor Route under BMP on HAM in the state of Andhra Pradesh." was awarded to BEKEM INFRA PROJECTS PVT. LTD. with an awarded contract value of ₹608.83 Cr.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹608.83 Cr (15.44% above the estimated PAC of ₹527.42 Cr).