Holistic Development of Surat Airport Including Extension of Apron and Terminal Building and construction of Parallel Taxi Track. SH. Hiring of technical manpower for execution of work Extension of apron and Construction of Parallel taxi track
Tender Specifications & Timeline
13 FieldsTotal Bidders
3
Lowest Bid (L1)
₹38.99 L
Estimated Value (PAC)
—
Margin vs Estimate
—
Completion Period
730 days
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | Samvit Buildcare Pvt.Ltd#205102 | ₹38.99 L | 0.0% (L1) | Rejected-Fin | Rejected-Finance |
| DQ | — | — | Rejected-Tech | Rejected-Technical | |
| DQ | jaykumar p. tilara#205200 | — | — | Rejected-Tech | Rejected-Technical |
This airports tender covers holistic Development of Surat Airport Including Extension of Apron and Terminal Building and construction of Parallel Taxi Track. SH. Hiring of technical manpower for execution of work Extension of apron and Construction of Parallel taxi track, issued by Airports Authority of India under reference AAI/SA/SM/NIT1/20-21. The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Surat Airport. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_62936.pdf
BOQ Comparative Chart
finsummary_62936.pdf
Shortfall document not submitted.
Shortfall document not submitted.
Quoted amount is on higher side of justified amount Hence not reasonable.
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
Geo Designs and Research Pvt Ltd #205226 | 05-Oct-2020 05:46 PM | Rejected-Technical Updated: 15-Oct-2020 04:43 PM | — | — | Shortfall document not submitted. |
jaykumar p. tilara #205200 | 05-Oct-2020 05:09 PM | Rejected-Technical Updated: 15-Oct-2020 04:43 PM | — | — | Shortfall document not submitted. |
Samvit Buildcare Pvt.Ltd #205102 | 05-Oct-2020 05:34 PM | Rejected-Finance Updated: 28-Oct-2020 01:44 PM | 38,98,800.00 | L1 | Quoted amount is on higher side of justified amount Hence not reasonable. |
Bid Evaluation Details & Logs
technical bid opening
Date: 12-Oct-2020 05:36 PM
Officer: Sanjay Sharma
Recommended for Asking Shortfall Documents as remarked against agency on E-Portal
technical evaluation
Date: 15-Oct-2020 04:43 PM
Officer: Sanjay Sharma
finance bid opening
Date: 28-Oct-2020 01:25 PM
Officer: Sanjay Sharma
The quoted amount of L1 agency is 8.39 percentage above justified cost.
finance evaluation
Date: 28-Oct-2020 01:44 PM
Officer: Sanjay Sharma
About This Procurement Notice
This central government tender was issued by Airports Authority of India. Bids must be submitted by 05-Oct-2020 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Holistic Development of Surat Airport Including Extension of Apron and Terminal "?
- The current status of this tender is "Expired". The submission deadline is 05-Oct-2020 06:00 PM. This information is sourced from official government procurement portals.
- QWho issued this central government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/SA/SM/NIT1/20-21. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value has not been disclosed for this procurement notice. Please refer to the official tender documents for detailed specifications.