Construction of Compound Wall surrounding balance area in AAI residential colony, Guwahati.
Tender Specifications & Timeline
13 FieldsTotal Bidders
10
Lowest Bid (L1)
₹84.25 L
Estimated Value (PAC)
₹1.28 Cr
Margin vs Estimate
-34.35%
Completion Period
120 days
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | BINOD KUMAR PRASAD#150984 | ₹84.25 L | 0.0% (L1) | -34.35% | Accepted-Finance |
| L2 | — | — | — | Not Admitted-Fee | |
| L2 | PANKAJ KUMAR DAS#150571 | ₹87.21 L | +3.52% | Rejected-Fin | Rejected-Finance |
| L3 | M/s Subhas Construction Co.#151412 | ₹88.88 L | +5.50% | Rejected-Fin | Rejected-Finance |
| L4 | M/s J H Associates#151571 | ₹93.08 L | +10.48% | Rejected-Fin | Rejected-Finance |
| L5 | Dhrubajyoti Kalita#151428 | ₹94.50 L | +12.17% | Rejected-Fin | Rejected-Finance |
| L6 | Dutta Construction and Co#151408 | ₹94.57 L | +12.25% | Rejected-Fin | Rejected-Finance |
| L7 | Sri Kajal Das#151489 | ₹97.32 L | +15.51% | Rejected-Fin | Rejected-Finance |
| L8 | Maa Kamakhya Infratech#151161 | ₹97.72 L | +15.99% | Rejected-Fin | Rejected-Finance |
| DQ | Partha Thakuria#151625 | — | — | Rejected-Tech | Rejected-Technical |
This airports tender covers construction of Compound Wall surrounding balance area in AAI residential colony, Guwahati., issued by Airports Authority of India under reference AAINERSMEC/GHY/BWall/NIT/19-20. The estimated contract value is ₹1.28 Cr, and the tender is currently Expired. Under financial bid evaluation, BINOD KUMAR PRASAD emerged as the lowest (L1) bidder with a quoted bid amount of ₹84.25 L.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in AAI Residential colony, LGBI Airport, Ghy. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_45693.pdf
finance_45693.pdf
BOQ Comparative Chart
finsummary_45693.pdf
Bidder emerged as L1
Bidder emerged as L5
Bidder emerged as L6
Bidder emerged as L8
Bidder emerged as L4
Bidder emerged as L3
EMD/Instrument is not valid
Bidder emerged as L2
Due to required documents are not submitted/uploaded in shortfall folder within stipulated time.
Bidder emerged as L7
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
BINOD KUMAR PRASAD #150984 | 29-Feb-2020 02:26 PM | Accepted-Finance Updated: 15-Sep-2020 11:50 AM | 84,24,620.00 | L1 | Bidder emerged as L1 |
Dhrubajyoti Kalita #151428 | 29-Feb-2020 05:31 PM | Rejected-Finance Updated: 15-Sep-2020 11:50 AM | 94,49,751.00 | L5 | Bidder emerged as L5 |
Dutta Construction and Co #151408 | 29-Feb-2020 02:20 PM | Rejected-Finance Updated: 15-Sep-2020 11:50 AM | 94,56,995.00 | L6 | Bidder emerged as L6 |
Maa Kamakhya Infratech #151161 | 29-Feb-2020 11:38 AM | Rejected-Finance Updated: 15-Sep-2020 11:50 AM | 97,71,956.00 | L8 | Bidder emerged as L8 |
M/s J H Associates #151571 | 29-Feb-2020 01:32 PM | Rejected-Finance Updated: 15-Sep-2020 11:50 AM | 93,07,920.00 | L4 | Bidder emerged as L4 |
M/s Subhas Construction Co. #151412 | 29-Feb-2020 05:51 PM | Rejected-Finance Updated: 15-Sep-2020 11:50 AM | 88,88,310.00 | L3 | Bidder emerged as L3 |
N K Construction And Suppliers #150966 | 29-Feb-2020 12:32 PM | Not Admitted-Fee Updated: 09-Mar-2020 06:53 PM | — | — | EMD/Instrument is not valid |
PANKAJ KUMAR DAS #150571 | 26-Feb-2020 09:13 PM | Rejected-Finance Updated: 15-Sep-2020 11:50 AM | 87,20,773.00 | L2 | Bidder emerged as L2 |
Partha Thakuria #151625 | 29-Feb-2020 04:49 PM | Rejected-Technical Updated: 23-Mar-2020 01:07 PM | — | — | Due to required documents are not submitted/uploaded in shortfall folder within stipulated time. |
Sri Kajal Das #151489 | 29-Feb-2020 11:33 AM | Rejected-Finance Updated: 15-Sep-2020 11:50 AM | 97,31,515.00 | L7 | Bidder emerged as L7 |
Bid Evaluation Details & Logs
technical bid opening
Date: 11-Mar-2020 12:16 PM
Officer: Ajit Saha
09 nos. of bids have been received and send for Tech. Evaluation process.
technical evaluation
Date: 23-Mar-2020 01:07 PM
Officer: Ajit Saha
finance bid opening
Date: 23-Mar-2020 04:45 PM
Officer: Ajit Saha
08 nos. of bid have been accepted and send for financial evaluation process.
finance evaluation
Date: 15-Sep-2020 11:50 AM
Officer: Ajit Saha
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹1.28 Cr. Bids must be submitted by 29-Feb-2020 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Construction of Compound Wall surrounding balance area in AAI residential colony"?
- The current status of this tender is "Expired". The submission deadline is 29-Feb-2020 06:00 PM. This information is sourced from official government procurement portals.
- QWho issued this central government tender?
- This tender was issued by Airports Authority of India. The reference number is AAINERSMEC/GHY/BWall/NIT/19-20. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹1.28 Cr. This is the approximate contract value as disclosed in the official tender document.
- QWho is the lowest (L1) bidder for this tender?
- Under financial bid evaluation for "Construction of Compound Wall surrounding balance area in AAI residential colony, Guwahati.", BINOD KUMAR PRASAD emerged as the lowest (L1) bidder with a quoted bid amount of ₹84.25 L. Full bid rankings and vendor comparisons are available on BiharInfraTales.