Resetting of Pontoon Bridge after repair and supplying of necesaary Iron material and Maintenance of Pontoon Bridge for five consecutive years i.e 2023-24, 2024-25, 2025-26, 2026-27 & 2027-28 (upto maintenance period) Dismentling of Pontoon bridge for the Alignment and storing the Pontoon sets at safe place on the side of River Embankment between Nainijor to Bihar ghat and Haldi village Diara acros river Ganga in Buxar District for during raining season and watching the Pontoon sets safely anchored along the Ganga river embankment during rainy season for six month as well as re-arranging the Pontoon sets when ever required due to increasing for six month as well as re-arranging the Pontoon sets when ever required due to increasing and decreasing of water level.
Tender Specifications & Timeline
17 FieldsPurchase Order & Contract Award
Official eProcurement award disclosure & contractor details
PO #46544
PO Date:2025-04-29
Work Commencement:2025-05-29
Validity / Expiry:2025-05-01
M/s SHRISTI DEVELOPERS PVT. LTD.
KRISHI UTPADAN BAZAR SAMITI, KATRA BAZAR,PATNA CITY
ii. Semi Skilled Labour
Purchase Order #
Official PO
Awarded Contract Value
₹14.94 Cr
Estimated Value (PAC)
₹16.56 Cr
Margin vs Estimate
-9.76%
Awarded Contractor (Official Order Recipient)
This bridges tender covers resetting of Pontoon Bridge after repair and supplying of necesaary Iron material and Maintenance of Pontoon Bridge for five consecutive years i.e 2023-24, 2024-25, 2025-26, 2026-27 & 2027-28 (upto maintenance period) Dismentling of Pontoon bridge for the Alignment and storing the Pontoon sets at safe place on the side of River Embankment between Nainijor to Bihar ghat and Haldi village Diara acros river Ganga in Buxar District for during raining season and watching the Pontoon sets safely anchored along the Ganga river embankment during rainy season for six month as well as re-arranging the Pontoon sets when ever required due to increasing for six month as well as re-arranging the Pontoon sets when ever required due to increasing and decreasing of water level., issued by Ram Bilas Yadav under reference BRPNN/ARA/748-GROUP-2/NAINIJOR. The estimated contract value is ₹16.56 Cr, and the tender is currently Expired. Following contract finalisation, the work was awarded to M/s SHRISTI DEVELOPERS PVT. LTD. under Purchase Order #46544 for a total value of ₹14.94 Cr.
This procurement is part of ongoing efforts by Bihar government departments to maintain and upgrade public infrastructure and services in Bihar. Vendors interested in similar opportunities can browse other tenders from the same issuing department below.
Authority & Contacts
Dealing / Issuing Officer
Mr Alok Kumar (EXECUTIVE ENGINEER)
Designation: Senior Project Engineer
Organization: BIHAR RAJYA PUL NIRMAN NIGAM LIMITED
Approving Authority
RAM BILAS YADAV
Designation: SENIOR PROJECT ENGINEER
Organization: BIHAR RAJYA PUL NIRMAN NIGAM LIMITED
About This Procurement Notice
This Bihar state government tender was issued by Ram Bilas Yadav. The estimated contract value is ₹16.56 Cr. Bids must be submitted by 2024-05-21 15:00:00.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Resetting of Pontoon Bridge after repair and supplying of necesaary Iron materia"?
- The current status of this tender is "Expired". The submission deadline is 2024-05-21 15:00:00. This information is sourced from official government procurement portals.
- QWho issued this Bihar government tender?
- This tender was issued by Ram Bilas Yadav. The reference number is BRPNN/ARA/748-GROUP-2/NAINIJOR. It is a Bihar state government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹16.56 Cr. This is the approximate contract value as disclosed in the official tender document.
- QWho won the contract for this tender?
- The contract for "Resetting of Pontoon Bridge after repair and supplying of necesaary Iron material and Maintenance of Pontoon Bridge for five consecutive years i.e 2023-24, 2024-25, 2025-26, 2026-27 & 2027-28 (upto maintenance period) Dismentling of Pontoon bridge for the Alignment and storing the Pontoon sets at safe place on the side of River Embankment between Nainijor to Bihar ghat and Haldi village Diara acros river Ganga in Buxar District for during raining season and watching the Pontoon sets safely anchored along the Ganga river embankment during rainy season for six month as well as re-arranging the Pontoon sets when ever required due to increasing for six month as well as re-arranging the Pontoon sets when ever required due to increasing and decreasing of water level." was awarded to M/s SHRISTI DEVELOPERS PVT. LTD. under Purchase Order #46544 with an awarded contract value of ₹14.94 Cr.
- QWhat is the final awarded contract value?
- The final awarded contract value is ₹14.94 Cr (9.74% below the estimated PAC of ₹16.56 Cr).