Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

Balance work of IRQP work in Rajwara- Tarauni to Dhoighat Road via Fardaha–Itharwa –Ammi-Majhigama-Dhabaila-Dhoighat Road from Km 0.00 To 17.20 (Total working length 14.80 Km) under RCD, Road Division Darbhanga for the year 2024-25 on Risk & Cost basis

#978
Road Division Darbhanga.
Road Circle Darbhanga.
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹10.82 Cr
Length17.20 km
Start09-07-2025
Completion31-12-2025
MDR · North Wing
Road Division Darbhanga.
Raj kishor Singh

Project Details

6 Fields
Project No.
978
Wing
North Wing
Division
Road Division Darbhanga.
Circle
Road Circle Darbhanga.
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹10.82 Cr
Sanctioned Length
17.20 km
Contractor
Raj kishor Singh
AA Date
31-08-2020
Start Date
09-07-2025
Expected Completion
31-12-2025

Balance work of IRQP work in Rajwara- Tarauni to Dhoighat Road via Fardaha–Itharwa –Ammi-Majhigama-Dhabaila-Dhoighat Road from Km 0.00 To 17.20 (Total working length 14.80 Km) under RCD, Road Division Darbhanga for the year 2024-25 on Risk & Cost basis is a Bihar Road Construction Department (RCD) project under Road Division Darbhanga., classified as a MDR. The agreement amount for this project is ₹10.82 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Completed. 1/22/0-01 No. completed. 2/22/0 completed.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Balance work of IRQP work in Rajwara- Tarauni to Dhoighat Road via Fardaha–Ithar"?
Status: Completed. This MDR project under Road Division Darbhanga. (Road Circle Darbhanga.) covers 17.20 km of road work. Expected completion: 31-12-2025.
QWho is the contractor for RCD project 978?
The contractor for this project is Raj kishor Singh. Project number: 978. Division: Road Division Darbhanga.. Administrative approval date: 31-08-2020.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Balance work of IRQP work in Rajwara- Tarauni to Dhoighat Ro" is ₹10.82 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Darbhanga..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 978 "Balance work of IRQP work in Rajwara- Tarauni to Dhoighat Ro" is one of thousands of road improvement and construction works tracked by BiharInfraTales.