| Project No. | 975 |
| Wing | North Wing |
| Division | Road Division Sheohar |
| Circle | North Bihar Road Circle Muzaffarpur |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹142.22 Cr |
| Sanctioned Length | 20.43 km |
| Contractor | M/S Ganesh Ram Dokania |
| AA Date | 16-01-2025 |
| Start Date | 25-11-2025 |
| Expected Completion | 24-11-2027 |
C&G, box cutting,Earth Work, GSB, Land Acquisation, Utility Shifting, Tree Translocation work in progress.
Superintending Engineer quality visit record
North Bihar Road Circle Muzaffarpur · Road Division Sheohar
Visited: 6 Mar 2026"Pots and patches found at some chainages. Instruction were given to make it motrable."