| Project No. | 861 |
| Wing | South Wing |
| Division | Road Division Biharsharif. |
| Circle | Central Road Circle Patna. |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹86.80 Cr |
| Sanctioned Length | 18.45 km |
| Contractor | M/s Sunny Engineering Works |
| AA Date | 28-02-2025 |
| Start Date | 08-08-2025 |
| Expected Completion | 07-02-2027 |
08 Nos of Box culvert comp and 04 Nos of Hume pipe is in progress . Drain is in progress and 01 No. H.L Bridge dismantling work is in progress. (Physical work completed - 16%). Site clearance/NOC - Processed by State Secretary for Recommendation after PSC-II. Pending at REC, Ranchi, Jharkhand Utility Shifting Status - Sanctioned copy of Utility shifting Estimate has received this office dated-09.01.2026
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Biharsharif.
Visited: 27 Jan 2026"Review meeting was Conducted on 27/01/2026. During meeting the condition of the road and ongoing works were reviewed, and necessary observations/instructions were communicated to the Executive Engineer and Contractor."