| Project No. | 860 |
| Wing | South Wing |
| Division | Road Division Biharsharif. |
| Circle | Central Road Circle Patna. |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹32.35 Cr |
| Sanctioned Length | 8.00 km |
| Contractor | M/S Surendra Pd. & Co. |
| AA Date | 05-03-2025 |
| Start Date | 09-03-2026 |
| Expected Completion | 08-03-2027 |
Work is in progress. (Physical work completed - 6%). Site clearance/NOC - Raise EDS for Non Forest Land has been compliance from this office. Pending at Nodal Officer due to EDS by State Secretary. Utility Shifting Status - Sanctioned copy of Utility shifting Estimate has received this office dated-12.01.2026.
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Biharsharif.
Visited: 27 Jan 2026"Review meeting was Conducted on 27/01/2026. During meeting the condition of the road and ongoing works were reviewed, and necessary observations/instructions were communicated to the Executive Engineer and Contractor."