| Project No. | 836 |
| Wing | South Wing |
| Division | Road Division Biharsharif. |
| Circle | Central Road Circle Patna. |
| Road Type | MDR |
| Head | PLAN |
| Agreement Value | ₹39.14 Cr |
| Sanctioned Length | 9.05 km |
| Contractor | RAJ KUMAR SINGH RAJA CONST. PVT. LTD. |
| AA Date | 24-01-2020 |
| Start Date | 22-01-2025 |
| Expected Completion | 21-07-2026 |
Due to L.A issue. Agreement has been closed by the order of Engineer-in-Chief vide letter no-8674(E) dated 24.12.2020. Presently re-tendering of balance quantity has been done. Total length of this road is 22.17 km break into two parts due to LA problem. Part II - Earth work, GSB & WMM is in progress. Also HP Culvert work, 2/33/0 and 2/22/0 culvert work and retaining walls is in progress. 3rd Revised T.S of amount Rs. 28720.46 Lac has been sanctioned by CE, South, vide letter no-381 dated 30.01.26 and submitted to Engineer in chief (HQ), RCD, Bihar, Patna for Revised AA which is still awaited. Because of Not provision of Utility Shifting, Raising/Shifting of Transmission Line and the Re-Carpating on old bituminous surface. (Physical work complete - 55%) Status of Utility/Transmission Line Shifting - Requisition for sanction copy of raising/shifting of Transmission line 03 Nos. by this office vide letter no-2234 dated 16.10.25. Which is pending at electricity department. LA Status - 83% LA is completed.
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Biharsharif.
Visited: 5 Jun 2025"निरीक्षण के क्रम में पाया गया कि मिट्टी का कार्य लगभग तीन किलोमीटर में किया गया है, शेष कार्य प्रगति पर है पथ में कुल 27 नंबर एचपी कन्वर्ट में से 16 नंबर एचपी कन्वर्ट का कार्य पूर्ण किया जा चुका है 17 वे एचपी कन्वर्ट का कार्य प्रगति में पाया गया. कार्यपालक अभियंता को निर्देश दिया गया कि कार्य में तेजी लाते हुए गुणवत्ता पूर्वक कार्य कराया जाए."