Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

Construction of Bihar Vetenary Science University Bypass Road from West of Comfed office to Mechanical Workshop Jagdeopath Road via BIT for the year 2023-24

#776
New Capital Road Division Patna.
Central Road Circle Patna.
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹6.28 Cr
Length0.74 km
Start19-10-2024
Completion31-05-2025
MDR · South Wing
New Capital Road Division Patna.
Barjendra Kumar Singh

Project Details

Project No.776
WingSouth Wing
DivisionNew Capital Road Division Patna.
CircleCentral Road Circle Patna.
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹6.28 Cr
Sanctioned Length0.74 km
ContractorBarjendra Kumar Singh
AA Date07-03-2024
Start Date19-10-2024
Expected Completion31-05-2025

Construction of Bihar Vetenary Science University Bypass Road from West of Comfed office to Mechanical Workshop Jagdeopath Road via BIT for the year 2023-24 is a Bihar Road Construction Department (RCD) project under New Capital Road Division Patna., classified as a MDR. The agreement amount for this project is ₹6.28 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work Completed

Frequently Asked Questions

What is the current status of the Bihar RCD project "Construction of Bihar Vetenary Science University Bypass Road from West of Comfe"?
Status: Completed. This MDR project under New Capital Road Division Patna. (Central Road Circle Patna.) covers 0.74 km of road work. Expected completion: 31-05-2025.
Who is the contractor for RCD project 776?
The contractor for this project is Barjendra Kumar Singh. Project number: 776. Division: New Capital Road Division Patna.. Administrative approval date: 07-03-2024.
What is the agreement value for this Bihar road project?
The agreement value for "Construction of Bihar Vetenary Science University Bypass Roa" is ₹6.28 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in New Capital Road Division Patna..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 776 "Construction of Bihar Vetenary Science University Bypass Roa" is one of thousands of road improvement and construction works tracked by BiharInfraTales.