MDRRCD BiharCompleted
NH-139 Jharkhand Border Maharajganj se Baluganj- Badhani-Deo-Ora-Sokya-Baghoi Railway Station –Deohara- Baghoigala-Deokund-Basatar- Keyal hote huye Mehandiya NH-98 Tak (Km 62.10 to 78.65) Package No. BR02RC304
#661
Road Division Aurangabad.
Magadh Road Circle Gaya
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹17.45 Cr
Length15.75 km
Start28-04-2023
Completion22-11-2023
MDR · South Wing
Road Division Aurangabad.
SAWAN RAJ CONSTRUCTION PVT LTD
Project Details
Project No.661
WingSouth Wing
DivisionRoad Division Aurangabad.
CircleMagadh Road Circle Gaya
Road TypeMDR
HeadState Plan
Cost & Timeline
Agreement Value₹17.45 Cr
Sanctioned Length15.75 km
ContractorSAWAN RAJ CONSTRUCTION PVT LTD
AA Date02-02-2022
Start Date28-04-2023
Expected Completion22-11-2023
NH-139 Jharkhand Border Maharajganj se Baluganj- Badhani-Deo-Ora-Sokya-Baghoi Railway Station –Deohara- Baghoigala-Deokund-Basatar- Keyal hote huye Mehandiya NH-98 Tak (Km 62.10 to 78.65) Package No. BR02RC304 is a Bihar Road Construction Department (RCD) project under Road Division Aurangabad., classified as a MDR. The agreement amount for this project is ₹17.45 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Construction work completed.
Frequently Asked Questions
- What is the current status of the Bihar RCD project "NH-139 Jharkhand Border Maharajganj se Baluganj- Badhani-Deo-Ora-Sokya-Baghoi Ra"?
- Status: Completed. This MDR project under Road Division Aurangabad. (Magadh Road Circle Gaya) covers 15.75 km of road work. Expected completion: 22-11-2023.
- Who is the contractor for RCD project 661?
- The contractor for this project is SAWAN RAJ CONSTRUCTION PVT LTD. Project number: 661. Division: Road Division Aurangabad.. Administrative approval date: 02-02-2022.
- What is the agreement value for this Bihar road project?
- The agreement value for "NH-139 Jharkhand Border Maharajganj se Baluganj- Badhani-Deo" is ₹17.45 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Aurangabad..
- What does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 661 "NH-139 Jharkhand Border Maharajganj se Baluganj- Badhani-Deo" is one of thousands of road improvement and construction works tracked by BiharInfraTales.