Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
SHRCD BiharCompleted

IRQP work in km 30.00 to 64.71 of SH-90

#647
Road Division Chapra.
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹49.46 Cr
Length34.71 km
Start20-02-2024
Completion19-02-2025
SH · North Wing
Road Division Chapra.
RAI RAJ CONSTRUCTION PRIVATE LIMITED

Project Details

Project No.647
WingNorth Wing
DivisionRoad Division Chapra.
CircleSaran Road Circle Hajipur.
Road TypeSH
HeadPLAN

Cost & Timeline

Agreement Value₹49.46 Cr
Sanctioned Length34.71 km
ContractorRAI RAJ CONSTRUCTION PRIVATE LIMITED
AA Date22-08-2023
Start Date20-02-2024
Expected Completion19-02-2025

IRQP work in km 30.00 to 64.71 of SH-90 is a Bihar Road Construction Department (RCD) project under Road Division Chapra., classified as a SH. The agreement amount for this project is ₹49.46 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work Completed

Frequently Asked Questions

What is the current status of the Bihar RCD project "IRQP work in km 30.00 to 64.71 of SH-90"?
Status: Completed. This SH project under Road Division Chapra. (Saran Road Circle Hajipur.) covers 34.71 km of road work. Expected completion: 19-02-2025.
Who is the contractor for RCD project 647?
The contractor for this project is RAI RAJ CONSTRUCTION PRIVATE LIMITED. Project number: 647. Division: Road Division Chapra.. Administrative approval date: 22-08-2023.
What is the agreement value for this Bihar road project?
The agreement value for "IRQP work in km 30.00 to 64.71 of SH-90" is ₹49.46 Cr. This is a SH project under Bihar Roads Construction Department (RCD) in Road Division Chapra..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 647 "IRQP work in km 30.00 to 64.71 of SH-90" is one of thousands of road improvement and construction works tracked by BiharInfraTales.