| Project No. | 449 |
| Wing | North Wing |
| Division | Road Division Motihari. |
| Circle | Road Circle Motihari |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹21.97 Cr |
| Sanctioned Length | 8.75 km |
| Contractor | Barhoniya Engicon Pvt. Ltd. |
| AA Date | 19-03-2020 |
| Start Date | 31-12-2021 |
| Expected Completion | 31-12-2025 |
(1) Road work completed . (2) Bridge Girder work complete, Bridge Deck slab work complete & Bridge approach work in progress. Bridge work in progress.
Superintending Engineer quality visit record
Road Circle Motihari · Road Division Motihari.
Visited: 30 Aug 2024"E/W-8.75KM, GSB-8.10KM, WMM, DGBM & BC-5.80KM, PQC-2.30KM, 13 NOS. RCC Box Culvert and 01 nos. HP Culvert work has been done. Progress work of RCC Drain is slow. All pile cap and Pier Shaft work done of 2 x 16m RCC HL Bridge in Ch.-3.960km."