| Project No. | 38 |
| Wing | South Wing |
| Division | Road Division Lakhisarai. |
| Circle | Road Circle Munger |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹44.12 Cr |
| Sanctioned Length | 23.09 km |
| Contractor | Palak Infra PVT LTD |
| AA Date | 01-09-2020 |
| Start Date | 13-04-2021 |
| Expected Completion | 31-05-2025 |
(1) Land acquisition in remaining 2.1 KM is under process. 2. The format prepared for publishing of khasara for land acquisition through Perpetual Lease method has been sent to the CO Pipariya and Barhiya for scrutiny. 3. BOQ shall be sent for approval for remaining work of 2.1 km very soon for tender.
Superintending Engineer quality visit record
Road Circle Munger · Road Division Lakhisarai.
Visited: 25 Jul 2024"यह पथ बड़हिया (कृष्णा चौक) से प्रारंभ होकर रामपुर चौक (NH-80) पर समाप्त हो जाती है। इस पथ की कुल लंबाई 21.10 कि0मी0 है। स्थल निरीक्षण के क्रम में सहायक अभियंता द्वारा बताया गया कि इस पथ में इंदूपुर के पास Ch-730 से 1000 तक Land Acquisition हेतु सतत् लीज पर जिला प्रसाशन द्वारा तय किये गये दर पर रैयत के द्वारा सहमति नही दी जा रही है। इस पथ के Ch-2600 से 3500 तक जैतूपुर के पास Existing Road पर रैयतों द्वारा काम नही करने दिया गया। चौड़ीकरण के लिए भूमि नही रहने के कारण मिट्टी का कार्य भी नही करने दिया गया। जिला पदाधिकारी द्वारा मौखिक रुप से अंचल अमीन को निदेशित करने पर अमीन स्थल की मापी कर रहा है। इस पथ के Ch-11400 से 11500 तक मुड़बरिया के पास भूमि विवाद के कारण पूर्व मार्ग रेखण (Alignment) से हटकर बनाने का दबाब दिये जाने के कारण Bituminous कार्य नही करने दिया गया। इस पथ के Ch-14600 से 15000 तक वलीपुर के पास भूमि विवाद के कारण कार्य नही किया गया। अंचल अधिकारी पिपरिया द्वारा नियुक्त अमीन एवं पुलिस बल के द्वारा मापी में भी काफी विरोध किया गया। इस प्रकार उक्त वर्णित चैनेजों पर कार्य बधित है। पथ का ROW कम रहने के कारण फ्लैंक की चौड़ाई कम है। उपस्थित कार्यपालक अभियंता एवं सहायक अभियंता को जिला प्रशासन से आपसी समन्वय बैठाकर कार्य पूर्ण करने हेतु निदेशित किया गया।"