| Project No. | 287 |
| Wing | South Wing |
| Division | Road Division Jehanabad. |
| Circle | Magadh Road Circle Gaya |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹6.17 Cr |
| Sanctioned Length | 0.35 km |
| Contractor | K ANDY & ASSOCIATES |
| AA Date | 06-07-2017 |
| Start Date | 01-10-2019 |
| Expected Completion | 30-06-2026 |
Construction of Bridge along with approach road have been completed except 30 m approach length due to L.A. issue. Six men committee constituted & rate fixed. Structural part of bridge completed & only 30m approach length remaining.
Superintending Engineer quality visit record
Magadh Road Circle Gaya · Road Division Jehanabad.
Visited: 22 Jan 2025"Attached Report"