MDRRCD BiharCompleted

Construction of road from Ashiyana more at Jawahar Lal Nehru marg (Fly over Piler No.-35) to BMP-5 and Aranya Bhawan at Shahid Ali Pir Khan Path-2 via Bihar Police Building construction office under New Capital Road Division R.C.D. Patna. (CMBD)

#250
New Capital Road Division Patna.
Central Road Circle Patna.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹15.57 Cr
Length1.71 km
Start01-11-2018
Completion31-03-2023
MDR · South Wing
New Capital Road Division Patna.
M/S Deo Construction

Project Details

6 Fields
Project No.
250
Wing
South Wing
Division
New Capital Road Division Patna.
Circle
Central Road Circle Patna.
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹15.57 Cr
Sanctioned Length
1.71 km
Contractor
M/S Deo Construction
AA Date
11-12-2017
Start Date
01-11-2018
Expected Completion
31-03-2023

Construction of road from Ashiyana more at Jawahar Lal Nehru marg (Fly over Piler No.-35) to BMP-5 and Aranya Bhawan at Shahid Ali Pir Khan Path-2 via Bihar Police Building construction office under New Capital Road Division R.C.D. Patna. (CMBD) is a Bihar Road Construction Department (RCD) project under New Capital Road Division Patna., classified as a MDR. The agreement amount for this project is ₹15.57 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

6m x 3m size box drain complete & in 28m length wall & deck slab work in progress.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Construction of road from Ashiyana more at Jawahar Lal Nehru marg (Fly over Pile"?
Status: Completed. This MDR project under New Capital Road Division Patna. (Central Road Circle Patna.) covers 1.71 km of road work. Expected completion: 31-03-2023.
QWho is the contractor for RCD project 250?
The contractor for this project is M/S Deo Construction. Project number: 250. Division: New Capital Road Division Patna.. Administrative approval date: 11-12-2017.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Construction of road from Ashiyana more at Jawahar Lal Nehru" is ₹15.57 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in New Capital Road Division Patna..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 250 "Construction of road from Ashiyana more at Jawahar Lal Nehru" is one of thousands of road improvement and construction works tracked by BiharInfraTales.