Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /RCD PMIS
  3. /Widening and Strengthening of Fariyani Chowk N.H.-
MDRRCD BiharCompleted

Widening and Strengthening of Fariyani Chowk N.H.-31 to Bahelia Asthan (Dhamdaha – Rupauli SH-65 Road) via Chapay, Kamakhya Asthan to Majra, Kakarjan, Murhi, Sahra road from km. 0.00 to 20.84

#198
Road Division Purnea.
Road Circle Purnea
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹38.11 Cr
Length20.84 km
Start06-03-2019
Completion30-04-2025
MDR · Simanchal Wing
Road Division Purnea.
SAI ENGICON AND CONSTRUCTION PRIVATE LIMITED

Project Details

Project No.198
WingSimanchal Wing
DivisionRoad Division Purnea.
CircleRoad Circle Purnea
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹38.11 Cr
Sanctioned Length20.84 km
ContractorSAI ENGICON AND CONSTRUCTION PRIVATE LIMITED
AA Date01-10-2018
Start Date06-03-2019
Expected Completion30-04-2025

Remarks

AS per Agreement work completed.

SE Inspection Log

Superintending Engineer quality visit record

Road Circle Purnea · Road Division Purnea.

Visited: 17 Apr 2025
"

"order to complete as early as possible"

Inspection Report PDF

Frequently Asked Questions

What is the current status of the Bihar RCD project "Widening and Strengthening of Fariyani Chowk N.H.-31 to Bahelia Asthan (Dhamdaha"?
Status: Completed. This MDR project under Road Division Purnea. (Road Circle Purnea) covers 20.84 km of road work. Expected completion: 30-04-2025.
Who is the contractor for RCD project 198?
The contractor for this project is SAI ENGICON AND CONSTRUCTION PRIVATE LIMITED. Project number: 198. Division: Road Division Purnea.. Administrative approval date: 01-10-2018.
What is the agreement value for this Bihar road project?
The agreement value for "Widening and Strengthening of Fariyani Chowk N.H.-31 to Bahe" is ₹38.11 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Purnea..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 198 "Widening and Strengthening of Fariyani Chowk N.H.-31 to Bahe" is one of thousands of road improvement and construction works tracked by BiharInfraTales.
Bihar RCD PMIS Dashboard

Related Resources

RCD

Bihar RCD PMIS Dashboard

All RCD road projects across Bihar

Roads

Bihar Road Network GIS Map

Visual map of Bihar highway and road network

NHAI

NHAI Drone Tracker

National highway drone-monitored progress

BRPNNL

BRPNNL Bridge Projects

Bihar bridge project monitor

Projects

Bihar Infrastructure Projects

All government infrastructure project tracker

Tenders

Bihar Government Tenders

Active procurement notices for road projects

IPM

Central Project Monitor (IPM)

Centrally-funded infrastructure in Bihar

Cabinet

Bihar Cabinet Decisions

Government policy for infrastructure projects

EC

Stage-1 EC Clearances

Forest and environmental clearances

Districts

Bihar District Data

District-level infrastructure and demographics

  1. BiharInfraTales
  2. /RCD PMIS
  3. /Widening and Strengthening of Fariyani Chowk N.H.-