MDRRCD BiharCompleted

Widening & Strengthening of NH- 101 Babar Ali Petrol pump to Sonwalia Dhala via Sisai-Safiyabad-Dharambari-Miratola –Pakadi More under Baikunthpur Block

#147
Road Division Gopalganj
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹29.73 Cr
Length11.99 km
Start08-06-2020
Completion07-06-2021
MDR · North Wing
Road Division Gopalganj
Bholeshankar Erection and Construction Private Limited

Project Details

6 Fields
Project No.
147
Wing
North Wing
Division
Road Division Gopalganj
Circle
Saran Road Circle Hajipur.
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹29.73 Cr
Sanctioned Length
11.99 km
Contractor
Bholeshankar Erection and Construction Private Limited
AA Date
21-02-2019
Start Date
08-06-2020
Expected Completion
07-06-2021

Widening & Strengthening of NH- 101 Babar Ali Petrol pump to Sonwalia Dhala via Sisai-Safiyabad-Dharambari-Miratola –Pakadi More under Baikunthpur Block is a Bihar Road Construction Department (RCD) project under Road Division Gopalganj, classified as a MDR. The agreement amount for this project is ₹29.73 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work Completed

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Widening & Strengthening of NH- 101 Babar Ali Petrol pump to Sonwalia Dhala via "?
Status: Completed. This MDR project under Road Division Gopalganj (Saran Road Circle Hajipur.) covers 11.99 km of road work. Expected completion: 07-06-2021.
QWho is the contractor for RCD project 147?
The contractor for this project is Bholeshankar Erection and Construction Private Limited. Project number: 147. Division: Road Division Gopalganj. Administrative approval date: 21-02-2019.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Widening & Strengthening of NH- 101 Babar Ali Petrol pump to" is ₹29.73 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gopalganj.
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 147 "Widening & Strengthening of NH- 101 Babar Ali Petrol pump to" is one of thousands of road improvement and construction works tracked by BiharInfraTales.