MDRRCD BiharOngoning

Widening & Strengthening of Road from Motihari Block office to Government bus Stand (NH-527D) Via Neharu Stadium, Health Centre including Drain under Road Division, Motihari for the year 2025-26

#1337
Road Division Motihari.
Road Circle Motihari
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹1.33 Cr
Length0.80 km
Start26-11-2025
Completion31-07-2026
MDR · North Wing
Road Division Motihari.
Sai Construction

Project Details

6 Fields
Project No.
1337
Wing
North Wing
Division
Road Division Motihari.
Circle
Road Circle Motihari
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹1.33 Cr
Sanctioned Length
0.80 km
Contractor
Sai Construction
AA Date
09-07-2025
Start Date
26-11-2025
Expected Completion
31-07-2026

Widening & Strengthening of Road from Motihari Block office to Government bus Stand (NH-527D) Via Neharu Stadium, Health Centre including Drain under Road Division, Motihari for the year 2025-26 is a Bihar Road Construction Department (RCD) project under Road Division Motihari., classified as a MDR. The agreement amount for this project is ₹1.33 Cr, and the current status is Ongoning.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Delay due to Utility Shifting work. Revised Estimate submitted for Utility shifting road work and drain work. 1 nos. CD under progress

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Widening & Strengthening of Road from Motihari Block office to Government bus St"?
Status: Ongoning. This MDR project under Road Division Motihari. (Road Circle Motihari) covers 0.80 km of road work. Expected completion: 31-07-2026.
QWho is the contractor for RCD project 1337?
The contractor for this project is Sai Construction. Project number: 1337. Division: Road Division Motihari.. Administrative approval date: 09-07-2025.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Widening & Strengthening of Road from Motihari Block office " is ₹1.33 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Motihari..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 1337 "Widening & Strengthening of Road from Motihari Block office " is one of thousands of road improvement and construction works tracked by BiharInfraTales.