Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

CONSTRUCTION OF FOURLANE NH-2 KHURMABAD TO GRAM TORNI BARAV JEHANABAD ROAD VIA ORAIYA, MASIHABAD, GOPALPUR, BORDER ROAD FROM KM 0.00 TO KM 10.50 ( PACKAGE NO.-BR28RC144)

#1327
Road Division Kochas
Bhojpur Road Circle Arrah.
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹13.24 Cr
Length10.50 km
Start06-02-2021
Completion05-05-2022
MDR · South Wing
Road Division Kochas
Pramod Kumar Singh

Project Details

Project No.1327
WingSouth Wing
DivisionRoad Division Kochas
CircleBhojpur Road Circle Arrah.
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹13.24 Cr
Sanctioned Length10.50 km
ContractorPramod Kumar Singh
AA Date31-08-2020
Start Date06-02-2021
Expected Completion05-05-2022

CONSTRUCTION OF FOURLANE NH-2 KHURMABAD TO GRAM TORNI BARAV JEHANABAD ROAD VIA ORAIYA, MASIHABAD, GOPALPUR, BORDER ROAD FROM KM 0.00 TO KM 10.50 ( PACKAGE NO.-BR28RC144) is a Bihar Road Construction Department (RCD) project under Road Division Kochas, classified as a MDR. The agreement amount for this project is ₹13.24 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Frequently Asked Questions

What is the current status of the Bihar RCD project "CONSTRUCTION OF FOURLANE NH-2 KHURMABAD TO GRAM TORNI BARAV JEHANABAD ROAD VIA O"?
Status: Completed. This MDR project under Road Division Kochas (Bhojpur Road Circle Arrah.) covers 10.50 km of road work. Expected completion: 05-05-2022.
Who is the contractor for RCD project 1327?
The contractor for this project is Pramod Kumar Singh. Project number: 1327. Division: Road Division Kochas. Administrative approval date: 31-08-2020.
What is the agreement value for this Bihar road project?
The agreement value for "CONSTRUCTION OF FOURLANE NH-2 KHURMABAD TO GRAM TORNI BARAV " is ₹13.24 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Kochas.
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 1327 "CONSTRUCTION OF FOURLANE NH-2 KHURMABAD TO GRAM TORNI BARAV " is one of thousands of road improvement and construction works tracked by BiharInfraTales.