Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharOngoning

Construction of RCC Drain & Paver-Block (Both Side) in Main Service Road from Motihari (NH-527D) Bariyarpur to Hawaai adda chowk and divider work in road from Balua flyover to Town thana via Sadar Hospital & town thana (petrol pump) to gayatri mandir under Road Division, Motihari for the year 2025-26

#1299
Road Division Motihari.
Road Circle Motihari
Bihar RCD PMIS — Road ProjectOngoning
Agreement₹10.36 Cr
Length0.45 km
Start24-01-2026
Completion30-10-2026
MDR · North Wing
Road Division Motihari.
Rishi Builders (I) Pvt. Ltd.

Project Details

Project No.1299
WingNorth Wing
DivisionRoad Division Motihari.
CircleRoad Circle Motihari
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹10.36 Cr
Sanctioned Length0.45 km
ContractorRishi Builders (I) Pvt. Ltd.
AA Date25-06-2025
Start Date24-01-2026
Expected Completion30-10-2026

Construction of RCC Drain & Paver-Block (Both Side) in Main Service Road from Motihari (NH-527D) Bariyarpur to Hawaai adda chowk and divider work in road from Balua flyover to Town thana via Sadar Hospital & town thana (petrol pump) to gayatri mandir under Road Division, Motihari for the year 2025-26 is a Bihar Road Construction Department (RCD) project under Road Division Motihari., classified as a MDR. The agreement amount for this project is ₹10.36 Cr, and the current status is Ongoning.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work in progress. Delay due to Utility Shifting. Delay due to Utility Shifting work. Revised estimate submitted for Utility Shifting, Road work.

Frequently Asked Questions

What is the current status of the Bihar RCD project "Construction of RCC Drain & Paver-Block (Both Side) in Main Service Road from Mo"?
Status: Ongoning. This MDR project under Road Division Motihari. (Road Circle Motihari) covers 0.45 km of road work. Expected completion: 30-10-2026.
Who is the contractor for RCD project 1299?
The contractor for this project is Rishi Builders (I) Pvt. Ltd.. Project number: 1299. Division: Road Division Motihari.. Administrative approval date: 25-06-2025.
What is the agreement value for this Bihar road project?
The agreement value for "Construction of RCC Drain & Paver-Block (Both Side) in Main " is ₹10.36 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Motihari..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 1299 "Construction of RCC Drain & Paver-Block (Both Side) in Main " is one of thousands of road improvement and construction works tracked by BiharInfraTales.