Construction of Type-II, Type-III, Type-IV, Quarters RCC tanks, FOB, RUB extension of minor bridges, approach road, development of circulating area and other miscellaneous works at different stations from Ghoswar Station (Km 5.50) to Harsidhi Bazar station (km 136.863) in connection with HJP-SGL New Rail Line Project
Estimate Cost
₹56.73 Cr
Sanctioned estimate
Tendered Cost
₹70.87 Cr
+24.9% vs estimate
Physical Progress
92%
Work completed
Status
Overdue
Current stage
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsConstruction of Type-II, Type-III, Type-IV, Quarters RCC tanks, FOB, RUB extension of minor bridges, approach road, development of circulating area and other miscellaneous works at different stations from Ghoswar Station (Km 5.50) to Harsidhi Bazar station (km 136.863) in connection with HJP-SGL New Rail Line Project is an East Central Railway (ECR) infrastructure work in Bihar, executed by Hari Construction and Associates Private Limited Keshawe. The tendered cost of the work is ₹70.87 Cr, and it is currently Overdue with physical progress recorded at 92%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Remarks
DOC under process
Frequently Asked Questions
- QWhat is the current status of the railway work "Construction of Type-II, Type-III, Type-IV, Quarters RCC tanks, FOB, RUB extensi"?
- Status: Overdue. This East Central Railway work is being executed by Hari Construction and Associates Private Limited Keshawe. Physical progress stands at 92%. Current date of completion (DOC): 31-03-2026.
- QWho is the agency for this Bihar railway project?
- The agency for this work is Hari Construction and Associates Private Limited Keshawe, Barauni, Begusarai, Bihar. Acceptance / agreement reference: ECR/CAO/Con/WT/Agt/29 Dated 08.01.2019. Work started on 27-09-2018.
- QWhat is the cost of this railway work?
- The tendered cost of "Construction of Type-II, Type-III, Type-IV, Quarters RCC tan" is ₹70.87 Cr (against an estimate of ₹56.73 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Type-II, Type-III, Type-IV, Quarters RCC tan" is one of hundreds of railway works covered.