East Central RailwayIn Progress

Construction of two girder bridges at Km 300/7-8 and Km 301/7-8 of 1x61m span OWG each between Valmikinagar Road station and Paniyahwa section in connection with operation of Railway line passing through Valmikinagar Tiger Reserve (VTR) in west champarn district.

Work #138
As of March 2026

Estimate Cost

₹34.04 Cr

Sanctioned estimate

Tendered Cost

₹35.11 Cr

+3.1% vs estimate

Physical Progress

60%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹35.11 Cr
Progress60%
Started25-10-2018
Target DOC31-05-2026
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE

Work Details

5 Fields
Work No.
138
Agency
Aditys-Chankya (JV) Flat no 102
Divya Apartmenr Ashiyana Digha road, Patna
Acceptance / LOA
LOA No ECR/CAO/Con/North/ETN 27-18-19/6191 dated 10.10.2018
Officer in Charge
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹34.04 Cr
Tendered Cost
₹35.11 Cr
Physical Progress
60%
Date Started
25-10-2018
Original DOC
31-05-2026
Extended DOC
N/A

Construction of two girder bridges at Km 300/7-8 and Km 301/7-8 of 1x61m span OWG each between Valmikinagar Road station and Paniyahwa section in connection with operation of Railway line passing through Valmikinagar Tiger Reserve (VTR) in west champarn district. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Aditys-Chankya (JV) Flat no 102. The tendered cost of the work is ₹35.11 Cr, and it is currently In Progress with physical progress recorded at 60%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of two girder bridges at Km 300/7-8 and Km 301/7-8 of 1x61m span OW"?
Status: In Progress. This East Central Railway work is being executed by M/s Aditys-Chankya (JV) Flat no 102. Physical progress stands at 60%. Current date of completion (DOC): 31-05-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Aditys-Chankya (JV) Flat no 102, Divya Apartmenr Ashiyana Digha road, Patna. Acceptance / agreement reference: LOA No ECR/CAO/Con/North/ETN 27-18-19/6191 dated 10.10.2018. Work started on 25-10-2018.
QWhat is the cost of this railway work?
The tendered cost of "Construction of two girder bridges at Km 300/7-8 and Km 301/" is ₹35.11 Cr (against an estimate of ₹34.04 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of two girder bridges at Km 300/7-8 and Km 301/" is one of hundreds of railway works covered.