East Central RailwayIn Progress

Supplying and spreading of blanketing material and ballast, BG track linking on diversion of Br. No. 45, 54 and 62 of RXL-NKE section including transportation of P.way material, dismantling of track, stacking of released materials in connection with Gauge conversion of JYG-DBG-NKE-BKF, section.

Estimate Cost

₹9.75 Cr

Sanctioned estimate

Tendered Cost

₹10.01 Cr

+2.7% vs estimate

Physical Progress

30%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹10.01 Cr
Progress30%
Started14-12-2022
Target DOC30-04-2026
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE

Work Details

5 Fields
Work No.
154
Acceptance / LOA
LOA No: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-36-22-23/00891750067769 Dated: 14/12/2022
Officer in Charge
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹9.75 Cr
Tendered Cost
₹10.01 Cr
Physical Progress
30%
Date Started
14-12-2022
Original DOC
30-04-2026
Extended DOC
N/A

Supplying and spreading of blanketing material and ballast, BG track linking on diversion of Br. No. 45, 54 and 62 of RXL-NKE section including transportation of P.way material, dismantling of track, stacking of released materials in connection with Gauge conversion of JYG-DBG-NKE-BKF, section. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s A K CONSTRUCTION BEGUSARAI BIHAT IBRAHIMPUR BEGUSARAI BEGU…. The tendered cost of the work is ₹10.01 Cr, and it is currently In Progress with physical progress recorded at 30%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supplying and spreading of blanketing material and ballast, BG track linking on "?
Status: In Progress. This East Central Railway work is being executed by M/s A K CONSTRUCTION BEGUSARAI BIHAT IBRAHIMPUR BEGUSARAI BEGU…. Physical progress stands at 30%. Current date of completion (DOC): 30-04-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s A K CONSTRUCTION BEGUSARAI BIHAT IBRAHIMPUR BEGUSARAI BEGUSARAI- 851135 Bihar, India. Acceptance / agreement reference: LOA No: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-36-22-23/00891750067769 Dated: 14/12/2022. Work started on 14-12-2022.
QWhat is the cost of this railway work?
The tendered cost of "Supplying and spreading of blanketing material and ballast, " is ₹10.01 Cr (against an estimate of ₹9.75 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supplying and spreading of blanketing material and ballast, " is one of hundreds of railway works covered.