Construction of substructure of Major Bridge No.16 UP (4x61m span OWG) on well foundation, Earthwork, Blanketing & Boulder Pitching in approaches, Transportation, Erection and Launching of 61.0 m span open web girder and other associated works of Major Bridge No. 16 UP (4x61m span-OWG) at Km 128/8-10 in connection with rebuilding of Bridge No-16 UP between Khagaria and Umeshnagar in Sonpur division.
Estimate Cost
₹59.85 Cr
Sanctioned estimate
Tendered Cost
₹55.00 Cr
-8.1% vs estimate
Physical Progress
15%
Work completed
Status
In Progress
Current stage
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsConstruction of substructure of Major Bridge No.16 UP (4x61m span OWG) on well foundation, Earthwork, Blanketing & Boulder Pitching in approaches, Transportation, Erection and Launching of 61.0 m span open web girder and other associated works of Major Bridge No. 16 UP (4x61m span-OWG) at Km 128/8-10 in connection with rebuilding of Bridge No-16 UP between Khagaria and Umeshnagar in Sonpur division. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Hari Construction and Associates Private Limited. The tendered cost of the work is ₹55.00 Cr, and it is currently In Progress with physical progress recorded at 15%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Frequently Asked Questions
- QWhat is the current status of the railway work "Construction of substructure of Major Bridge No.16 UP (4x61m span OWG) on well f"?
- Status: In Progress. This East Central Railway work is being executed by M/s Hari Construction and Associates Private Limited. Physical progress stands at 15%. Current date of completion (DOC): 31-03-2027.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/s Hari Construction and Associates Private Limited, Begusarai, Keshawe, Barauni, Begusarai-851134. Acceptance / agreement reference: 05.10.2023. Work started on 05-11-2023.
- QWhat is the cost of this railway work?
- The tendered cost of "Construction of substructure of Major Bridge No.16 UP (4x61m" is ₹55.00 Cr (against an estimate of ₹59.85 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of substructure of Major Bridge No.16 UP (4x61m" is one of hundreds of railway works covered.