East Central RailwayCompleted

Construction of substructure of Major Br. No. 30 (7 x 12.20 m - Composite Girder) on Pile Foundation & Construction of Major Br. No. 35 (6 x 6.10 m - PSC Slabs) and Br.No. 2 (3 x 6.10 m - PSC Slabs) on Open/Raft Foundation, Construction of deck Slabs, retaining wall, etc. between Kakarghati & Shisho stations in connection with Construction of Darbhanga Bye-Pass Line.

Work #5
As of March 2026

Estimate Cost

N/A

Sanctioned estimate

Tendered Cost

₹40.63 Cr

Awarded value

Physical Progress

90%

Work completed

Status

Completed

Current stage

East Central Railway — CAO (Con)Completed
Tendered₹40.63 Cr
Progress90%
Started05-02-2021
Target DOC30-11-2024
Mahboob Alam CE/C/NC/MHX; Vinod Kumar Gupta, Dy CE/C/I/SPJ; Vijay Shankar Singh, AEN/C/SPJ

Work Details

5 Fields
Work No.
5
Agency
JYOTI S P MALIK JV-KOLKATA 34 A
METCALF STREET 4TH FLOOR KOLKATA-700013 West Bengal, India
Acceptance / LOA
ECR-CAO-C-N-ETN-9-20-21/01020480025602 dt 14/09/20 ** ECR/CAO/Con/WT/Agt/148 dt. 08/12/2020
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Vinod Kumar Gupta, Dy CE/C/I/SPJ; Vijay Shankar Singh, AEN/C/SPJ
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
N/A
Tendered Cost
₹40.63 Cr
Physical Progress
90%
Date Started
05-02-2021
Original DOC
13-03-2022
Extended DOC
30-11-2024

Construction of substructure of Major Br. No. 30 (7 x 12.20 m - Composite Girder) on Pile Foundation & Construction of Major Br. No. 35 (6 x 6.10 m - PSC Slabs) and Br.No. 2 (3 x 6.10 m - PSC Slabs) on Open/Raft Foundation, Construction of deck Slabs, retaining wall, etc. between Kakarghati & Shisho stations in connection with Construction of Darbhanga Bye-Pass Line. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s JYOTI S P MALIK JV-KOLKATA 34 A. The tendered cost of the work is ₹40.63 Cr, and it is currently Completed with physical progress recorded at 90%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work Completed

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of substructure of Major Br. No. 30 (7 x 12.20 m - Composite Girder"?
Status: Completed. This East Central Railway work is being executed by M/s JYOTI S P MALIK JV-KOLKATA 34 A. Physical progress stands at 90%. Current date of completion (DOC): 30-11-2024.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s JYOTI S P MALIK JV-KOLKATA 34 A, METCALF STREET 4TH FLOOR KOLKATA-700013 West Bengal, India. Acceptance / agreement reference: ECR-CAO-C-N-ETN-9-20-21/01020480025602 dt 14/09/20 ** ECR/CAO/Con/WT/Agt/148 dt. 08/12/2020. Work started on 05-02-2021.
QWhat is the cost of this railway work?
The tendered cost of "Construction of substructure of Major Br. No. 30 (7 x 12.20 " is ₹40.63 Cr. This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of substructure of Major Br. No. 30 (7 x 12.20 " is one of hundreds of railway works covered.