East Central RailwayIn Progress

Construction of Station cum S&T building Passenger Platform, Station approach roads, yard drains, circulating area, Deep tube well, other allied and miscellaneous works between Harinagar (excluding) to Valmikinagar road station (including) in connection with NKE-VKNR doubling project.

Work #323
As of June 2026

Estimate Cost

₹28.82 Cr

Sanctioned estimate

Tendered Cost

₹32.97 Cr

+14.4% vs estimate

Physical Progress

72%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹32.97 Cr
Progress72%
Started15-03-2020
Target DOC30-11-2026
Vijay Kumar, CE/C/NE/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Harinandan Ram, AEN/C/NKE

Work Details

5 Fields
Work No.
323
Agency
Chanakya Technos Private Limited
D-7, Lane-2, Vijay Nagar, Rukanpura, Bailey Road, Patna
Acceptance / LOA
LOA No. ECR/CAO/CON/NORTH/ETN-95-19-20 date 24.02.2020
Officer in Charge
Vijay Kumar, CE/C/NE/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Harinandan Ram, AEN/C/NKE
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹28.82 Cr
Tendered Cost
₹32.97 Cr
Physical Progress
72%
Date Started
15-03-2020
Original DOC
30-11-2026
Extended DOC
N/A

Construction of Station cum S&T building Passenger Platform, Station approach roads, yard drains, circulating area, Deep tube well, other allied and miscellaneous works between Harinagar (excluding) to Valmikinagar road station (including) in connection with NKE-VKNR doubling project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Chanakya Technos Private Limited. The tendered cost of the work is ₹32.97 Cr, and it is currently In Progress with physical progress recorded at 72%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Station cum S&T building Passenger Platform, Station approach ro"?
Status: In Progress. This East Central Railway work is being executed by M/s Chanakya Technos Private Limited. Physical progress stands at 72%. Current date of completion (DOC): 30-11-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Chanakya Technos Private Limited, D-7, Lane-2, Vijay Nagar, Rukanpura, Bailey Road, Patna. Acceptance / agreement reference: LOA No. ECR/CAO/CON/NORTH/ETN-95-19-20 date 24.02.2020. Work started on 15-03-2020.
QWhat is the cost of this railway work?
The tendered cost of "Construction of Station cum S&T building Passenger Platform," is ₹32.97 Cr (against an estimate of ₹28.82 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Station cum S&T building Passenger Platform," is one of hundreds of railway works covered.