East Central RailwayOverdue

Construction of RRI and other Signal Building-Earthwork for platform & Roads 6.10m wide foot over Bridge, passenger platform, Shelter, yard Drains, Coach, Washing pit construction of gate lodges and other S&T Building between Barauni to Bachhwara.

Work #25
As of March 2026

Estimate Cost

₹57.05 Cr

Sanctioned estimate

Tendered Cost

₹47.21 Cr

-17.2% vs estimate

Physical Progress

36%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹47.21 Cr
Progress36%
Started09-02-2023
Target DOC03-02-2026
Mahboob Alam CE/C/NC/MHX; Avinash Sahani. Dy.CE/C/II/SPJ

Work Details

5 Fields
Work No.
25
Acceptance / LOA
00868500083493 dt. 03.08.2023
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Avinash Sahani. Dy.CE/C/II/SPJ
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹57.05 Cr
Tendered Cost
₹47.21 Cr
Physical Progress
36%
Date Started
09-02-2023
Original DOC
03-02-2026
Extended DOC
N/A

Construction of RRI and other Signal Building-Earthwork for platform & Roads 6.10m wide foot over Bridge, passenger platform, Shelter, yard Drains, Coach, Washing pit construction of gate lodges and other S&T Building between Barauni to Bachhwara. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Bateshwar Singh Bihat Begusarai. The tendered cost of the work is ₹47.21 Cr, and it is currently Overdue with physical progress recorded at 36%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of RRI and other Signal Building-Earthwork for platform & Roads 6.1"?
Status: Overdue (overdue). This East Central Railway work is being executed by M/s Bateshwar Singh Bihat Begusarai. Physical progress stands at 36%. Current date of completion (DOC): 03-02-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Bateshwar Singh Bihat Begusarai. Acceptance / agreement reference: 00868500083493 dt. 03.08.2023. Work started on 09-02-2023.
QWhat is the cost of this railway work?
The tendered cost of "Construction of RRI and other Signal Building-Earthwork for " is ₹47.21 Cr (against an estimate of ₹57.05 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of RRI and other Signal Building-Earthwork for " is one of hundreds of railway works covered.