Construction of RRI and other Signal Building-Earthwork for platform & Roads 6.10m wide foot over Bridge, passenger platform, Shelter, yard Drains, Coach, Washing pit construction of gate lodges and other S&T Building between Barauni to Bachhwara.
Estimate Cost
₹57.05 Cr
Sanctioned estimate
Tendered Cost
₹47.21 Cr
-17.2% vs estimate
Physical Progress
36%
Work completed
Status
Overdue
Past target DOC
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsConstruction of RRI and other Signal Building-Earthwork for platform & Roads 6.10m wide foot over Bridge, passenger platform, Shelter, yard Drains, Coach, Washing pit construction of gate lodges and other S&T Building between Barauni to Bachhwara. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Bateshwar Singh Bihat Begusarai. The tendered cost of the work is ₹47.21 Cr, and it is currently Overdue with physical progress recorded at 36%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Remarks
DOC under process
Frequently Asked Questions
- QWhat is the current status of the railway work "Construction of RRI and other Signal Building-Earthwork for platform & Roads 6.1"?
- Status: Overdue (overdue). This East Central Railway work is being executed by M/s Bateshwar Singh Bihat Begusarai. Physical progress stands at 36%. Current date of completion (DOC): 03-02-2026.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/s Bateshwar Singh Bihat Begusarai. Acceptance / agreement reference: 00868500083493 dt. 03.08.2023. Work started on 09-02-2023.
- QWhat is the cost of this railway work?
- The tendered cost of "Construction of RRI and other Signal Building-Earthwork for " is ₹47.21 Cr (against an estimate of ₹57.05 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of RRI and other Signal Building-Earthwork for " is one of hundreds of railway works covered.