Balance work of Jhanjharpur-Laukaha Bazar section such as PP Shed, Low Cost shed, Seating arrangement, Platform and LC fencing, Cess repair, Deeper Drop/Curtain wall at Major Br No. 21A, Side Pathway at Major Br No. 7A (3x12.2m PG), Major Br No. 40 (4x18.3m PG) and Major Br No. 45 (2x18.3m), Approach road from LHS No. 25 to VPH Railway station, platform slope drains at CDNA & VPH and inspection steps at 15nos LHS from MHRL to LKQ etc. & Balance work of (G+3) 12 units Type-II qtrs. at NMA in Samastipur Division of East Central Railway.
Estimate Cost
₹15.26 Cr
Sanctioned estimate
Tendered Cost
₹12.70 Cr
-16.8% vs estimate
Physical Progress
50%
Work completed
Status
In Progress
Current stage
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsBalance work of Jhanjharpur-Laukaha Bazar section such as PP Shed, Low Cost shed, Seating arrangement, Platform and LC fencing, Cess repair, Deeper Drop/Curtain wall at Major Br No. 21A, Side Pathway at Major Br No. 7A (3x12.2m PG), Major Br No. 40 (4x18.3m PG) and Major Br No. 45 (2x18.3m), Approach road from LHS No. 25 to VPH Railway station, platform slope drains at CDNA & VPH and inspection steps at 15nos LHS from MHRL to LKQ etc. & Balance work of (G+3) 12 units Type-II qtrs. at NMA in Samastipur Division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s MAA BHAGWATI CONSTRUCTION-BEGUSARAI AT MADHURAPUR BICHLA T…. The tendered cost of the work is ₹12.70 Cr, and it is currently In Progress with physical progress recorded at 50%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Remarks
Work In progress
Frequently Asked Questions
- QWhat is the current status of the railway work "Balance work of Jhanjharpur-Laukaha Bazar section such as PP Shed, Low Cost shed"?
- Status: In Progress. This East Central Railway work is being executed by M/s MAA BHAGWATI CONSTRUCTION-BEGUSARAI AT MADHURAPUR BICHLA T…. Physical progress stands at 50%. Current date of completion (DOC): 30-04-2026.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/s MAA BHAGWATI CONSTRUCTION-BEGUSARAI AT MADHURAPUR BICHLA TOLA PO BARAUNI DEODHI PS TEGHRA BEGUSARAI- 851113 Bihar, India. Acceptance / agreement reference: LOA No. 01110900123643 dt. 17.02.2025 CA No. ECR/ECRC/Civil/2025/0024 dt 19.05.2025. Work started on 11-04-2025.
- QWhat is the cost of this railway work?
- The tendered cost of "Balance work of Jhanjharpur-Laukaha Bazar section such as PP" is ₹12.70 Cr (against an estimate of ₹15.26 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Balance work of Jhanjharpur-Laukaha Bazar section such as PP" is one of hundreds of railway works covered.