Construction of Formation, Minor bridges, RUB/LHS, Station building at New Jhajha & Baijnathpur Andauli, Gate lodge and other ancillary works in connection with New Bypass Line at Saraigarh in between New Jhajha to Baijnathpur Andauli station in Samastipur division of East Central Railway.
Estimate Cost
₹27.44 Cr
Sanctioned estimate
Tendered Cost
₹29.71 Cr
+8.3% vs estimate
Physical Progress
97%
Work completed
Status
In Progress
Current stage
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsConstruction of Formation, Minor bridges, RUB/LHS, Station building at New Jhajha & Baijnathpur Andauli, Gate lodge and other ancillary works in connection with New Bypass Line at Saraigarh in between New Jhajha to Baijnathpur Andauli station in Samastipur division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/S Lall Construction India Limited-New Delhi. The tendered cost of the work is ₹29.71 Cr, and it is currently In Progress with physical progress recorded at 97%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Frequently Asked Questions
- QWhat is the current status of the railway work "Construction of Formation, Minor bridges, RUB/LHS, Station building at New Jhajh"?
- Status: In Progress. This East Central Railway work is being executed by M/S Lall Construction India Limited-New Delhi. Physical progress stands at 97%. Current date of completion (DOC): 30-08-2026.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/S Lall Construction India Limited-New Delhi, Third Floor, Plot No. 28, Karuna Kunj, Sector 03 Dwarka, New Delhi-110075. Acceptance / agreement reference: LOA No. 00866770091492 dt 22.11.2023; CA No. ECR/ECRC/Civil/2024/0020 dt 19.03.24. Work started on 04-12-2023.
- QWhat is the cost of this railway work?
- The tendered cost of "Construction of Formation, Minor bridges, RUB/LHS, Station b" is ₹29.71 Cr (against an estimate of ₹27.44 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Formation, Minor bridges, RUB/LHS, Station b" is one of hundreds of railway works covered.