East Central RailwayIn Progress

Construction of Formation, Minor bridges, RUB/LHS, Station building at New Jhajha & Baijnathpur Andauli, Gate lodge and other ancillary works in connection with New Bypass Line at Saraigarh in between New Jhajha to Baijnathpur Andauli station in Samastipur division of East Central Railway.

Estimate Cost

₹27.44 Cr

Sanctioned estimate

Tendered Cost

₹29.71 Cr

+8.3% vs estimate

Physical Progress

97%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹29.71 Cr
Progress97%
Started04-12-2023
Target DOC30-08-2026
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Vinod Kumar, AXEN/Con/DBG

Work Details

5 Fields
Work No.
255
Agency
Lall Construction India Limited-New Delhi, Third Floor
Plot No. 28, Karuna Kunj, Sector 03 Dwarka, New Delhi-110075
Acceptance / LOA
LOA No. 00866770091492 dt 22.11.2023; CA No. ECR/ECRC/Civil/2024/0020 dt 19.03.24
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Vinod Kumar, AXEN/Con/DBG
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹27.44 Cr
Tendered Cost
₹29.71 Cr
Physical Progress
97%
Date Started
04-12-2023
Original DOC
21-11-2024
Extended DOC
30-08-2026

Construction of Formation, Minor bridges, RUB/LHS, Station building at New Jhajha & Baijnathpur Andauli, Gate lodge and other ancillary works in connection with New Bypass Line at Saraigarh in between New Jhajha to Baijnathpur Andauli station in Samastipur division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/S Lall Construction India Limited-New Delhi. The tendered cost of the work is ₹29.71 Cr, and it is currently In Progress with physical progress recorded at 97%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Formation, Minor bridges, RUB/LHS, Station building at New Jhajh"?
Status: In Progress. This East Central Railway work is being executed by M/S Lall Construction India Limited-New Delhi. Physical progress stands at 97%. Current date of completion (DOC): 30-08-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/S Lall Construction India Limited-New Delhi, Third Floor, Plot No. 28, Karuna Kunj, Sector 03 Dwarka, New Delhi-110075. Acceptance / agreement reference: LOA No. 00866770091492 dt 22.11.2023; CA No. ECR/ECRC/Civil/2024/0020 dt 19.03.24. Work started on 04-12-2023.
QWhat is the cost of this railway work?
The tendered cost of "Construction of Formation, Minor bridges, RUB/LHS, Station b" is ₹29.71 Cr (against an estimate of ₹27.44 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Formation, Minor bridges, RUB/LHS, Station b" is one of hundreds of railway works covered.