East Central RailwayIn Progress

Construction of foot over bridge at Kaparpura, Kanti, Piprahan, Motipur, Mahwal, Mehsi, Chakia, Pipra, Jiwdhara, Bapudham Motihari, & Semra Stations in connection with MFP-SGL doubling project

Work #265
As of June 2026

Estimate Cost

₹23.17 Cr

Sanctioned estimate

Tendered Cost

₹21.63 Cr

-6.6% vs estimate

Physical Progress

35%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹21.63 Cr
Progress35%
Started30-04-2020
Target DOC20-09-2026
Indrajit Kumar, CE/C/NW/MHX; Avanish Sonu, Dy CE/C/I/HJP; Sri. Ravi Shankar Singh (AEN/Con/MFP-I)

Work Details

5 Fields
Work No.
265
Agency
Brij Nandan Singh-Asansol, Triveni-A
Flat No.-1D, Shristinagar, Asansol-713305
Acceptance / LOA
LOA no CAO-C-HQ-Engineering ECR-CAO-C-N-ETN-79-19-20/00853500012916/56 dt. 02.01.2020
Officer in Charge
Indrajit Kumar, CE/C/NW/MHX; Avanish Sonu, Dy CE/C/I/HJP; Sri. Ravi Shankar Singh (AEN/Con/MFP-I)
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹23.17 Cr
Tendered Cost
₹21.63 Cr
Physical Progress
35%
Date Started
30-04-2020
Original DOC
01-01-2021
Extended DOC
20-09-2026

Construction of foot over bridge at Kaparpura, Kanti, Piprahan, Motipur, Mahwal, Mehsi, Chakia, Pipra, Jiwdhara, Bapudham Motihari, & Semra Stations in connection with MFP-SGL doubling project is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Brij Nandan Singh-Asansol. The tendered cost of the work is ₹21.63 Cr, and it is currently In Progress with physical progress recorded at 35%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of foot over bridge at Kaparpura, Kanti, Piprahan, Motipur, Mahwal,"?
Status: In Progress. This East Central Railway work is being executed by M/s Brij Nandan Singh-Asansol. Physical progress stands at 35%. Current date of completion (DOC): 20-09-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Brij Nandan Singh-Asansol, Triveni-A, Flat No.-1D, Shristinagar, Asansol-713305. Acceptance / agreement reference: LOA no CAO-C-HQ-Engineering ECR-CAO-C-N-ETN-79-19-20/00853500012916/56 dt. 02.01.2020. Work started on 30-04-2020.
QWhat is the cost of this railway work?
The tendered cost of "Construction of foot over bridge at Kaparpura, Kanti, Piprah" is ₹21.63 Cr (against an estimate of ₹23.17 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of foot over bridge at Kaparpura, Kanti, Piprah" is one of hundreds of railway works covered.