East Central RailwayOverdue

Final Location Survey (FLS) for Doubling Line between Narkatiaganj-Raxaul-Sitamarhi-Darbhanga & Sitamarhi-Muzaffarpur section (approx. 255.5 Kms.) and FLS for 3rd & 4th line between Barauni-Bachhwara including Barauni Yard Remodeling (approx. 16 Kms.), Carrying out detail Engineering survey including Leveling, alignment, soil exploration, preparation of plans, L-section, GA plans of Bridges etc., bill of quantities and other related ancillary activities in connection with preparation of DPR in Samastipur division.

Estimate Cost

₹2.53 Cr

Sanctioned estimate

Tendered Cost

₹2.40 Cr

-5.1% vs estimate

Physical Progress

60%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹2.40 Cr
Progress60%
Started04-11-2020
Target DOC20-01-2026
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE

Work Details

5 Fields
Work No.
136
Agency
Matrix Gio Solution Pvt. Ltd., New Delhi 47, Sector-13
Pocket-B, Phase-2, Dwarka, New Delhi-110078.
Acceptance / LOA
ECR/CAO/CON/WT/Agt/149 dated 25.01.2021
Officer in Charge
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹2.53 Cr
Tendered Cost
₹2.40 Cr
Physical Progress
60%
Date Started
04-11-2020
Original DOC
20-01-2026
Extended DOC
N/A

Final Location Survey (FLS) for Doubling Line between Narkatiaganj-Raxaul-Sitamarhi-Darbhanga & Sitamarhi-Muzaffarpur section (approx. 255.5 Kms.) and FLS for 3rd & 4th line between Barauni-Bachhwara including Barauni Yard Remodeling (approx. 16 Kms.), Carrying out detail Engineering survey including Leveling, alignment, soil exploration, preparation of plans, L-section, GA plans of Bridges etc., bill of quantities and other related ancillary activities in connection with preparation of DPR in Samastipur division. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/S Matrix Gio Solution Pvt. Ltd.. The tendered cost of the work is ₹2.40 Cr, and it is currently Overdue with physical progress recorded at 60%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Final Location Survey (FLS) for Doubling Line between Narkatiaganj-Raxaul-Sitama"?
Status: Overdue (overdue). This East Central Railway work is being executed by M/S Matrix Gio Solution Pvt. Ltd.. Physical progress stands at 60%. Current date of completion (DOC): 20-01-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/S Matrix Gio Solution Pvt. Ltd., New Delhi 47, Sector-13, Pocket-B, Phase-2, Dwarka, New Delhi-110078.. Acceptance / agreement reference: ECR/CAO/CON/WT/Agt/149 dated 25.01.2021. Work started on 04-11-2020.
QWhat is the cost of this railway work?
The tendered cost of "Final Location Survey (FLS) for Doubling Line between Narkat" is ₹2.40 Cr (against an estimate of ₹2.53 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Final Location Survey (FLS) for Doubling Line between Narkat" is one of hundreds of railway works covered.