East Central RailwayOverdue

Earthwork in filling in embankment, blanketing, p.way work, extension of bridges, PF wall, extension of FOB, boundary wall etc for the construction of Line No. 4 at Ghoswar in connection with New BG Rail Line HJP SGL project.

Work #274
As of June 2026

Estimate Cost

₹8.12 Cr

Sanctioned estimate

Tendered Cost

₹6.95 Cr

-14.4% vs estimate

Physical Progress

25%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹6.95 Cr
Progress25%
Started17-06-2021
Target DOC15-06-2025
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
274
Agency
Lord Vishnu Construction Pvt. Ltd
101 Lotus Apartment, New Patliputra Colony, Patna-800014
Acceptance / LOA
ECR/CAO/Con/WT/Agt/165 dt 17.06.21
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹8.12 Cr
Tendered Cost
₹6.95 Cr
Physical Progress
25%
Date Started
17-06-2021
Original DOC
10-02-2022
Extended DOC
15-06-2025

Earthwork in filling in embankment, blanketing, p.way work, extension of bridges, PF wall, extension of FOB, boundary wall etc for the construction of Line No. 4 at Ghoswar in connection with New BG Rail Line HJP SGL project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Lord Vishnu Construction Pvt. Ltd.. The tendered cost of the work is ₹6.95 Cr, and it is currently Overdue with physical progress recorded at 25%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork in filling in embankment, blanketing, p.way work, extension of bridges"?
Status: Overdue (overdue). This East Central Railway work is being executed by Lord Vishnu Construction Pvt. Ltd.. Physical progress stands at 25%. Current date of completion (DOC): 15-06-2025.
QWho is the agency for this Bihar railway project?
The agency for this work is Lord Vishnu Construction Pvt. Ltd, 101 Lotus Apartment, New Patliputra Colony, Patna-800014. Acceptance / agreement reference: ECR/CAO/Con/WT/Agt/165 dt 17.06.21. Work started on 17-06-2021.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork in filling in embankment, blanketing, p.way work, " is ₹6.95 Cr (against an estimate of ₹8.12 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in filling in embankment, blanketing, p.way work, " is one of hundreds of railway works covered.