East Central RailwayFinal Bill / Closure

Erection, launching & transportation of girder on remaining Major bridges and other allied work, between Saraigarh to Forbesganj section in connection with GC work of Saharsa-Forbesganj station in samastipur division of E.C. Railway.

Work #50
As of March 2026

Estimate Cost

₹3.11 Cr

Sanctioned estimate

Tendered Cost

₹3.05 Cr

-1.9% vs estimate

Physical Progress

53%

Work completed

Status

Final Bill / Closure

Current stage

East Central Railway — CAO (Con)Final Bill / Closure
Tendered₹3.05 Cr
Progress53%
Started01-09-2023
Target DOC31-01-2026
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri A K Sinha AEN/C/DBG

Work Details

5 Fields
Work No.
50
Acceptance / LOA
ECR-CAO-C-N-ETN-05-23-24/10375900081520 Dtd 14.07.2023 CA-ECR/ECRC/Civil/2023/0046 Dt 13.11.2023
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Sri Pankaj Kumar Dy CE/C/III/SPJ; Sri A K Sinha AEN/C/DBG
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹3.11 Cr
Tendered Cost
₹3.05 Cr
Physical Progress
53%
Date Started
01-09-2023
Original DOC
31-01-2026
Extended DOC
N/A

Erection, launching & transportation of girder on remaining Major bridges and other allied work, between Saraigarh to Forbesganj section in connection with GC work of Saharsa-Forbesganj station in samastipur division of E.C. Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s BRBA INFRATECH LLP. The tendered cost of the work is ₹3.05 Cr, and it is currently Final Bill / Closure with physical progress recorded at 53%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work completed. Final variation is under process.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Erection, launching & transportation of girder on remaining Major bridges and ot"?
Status: Final Bill / Closure. This East Central Railway work is being executed by M/s BRBA INFRATECH LLP. Physical progress stands at 53%. Current date of completion (DOC): 31-01-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s BRBA INFRATECH LLP. Acceptance / agreement reference: ECR-CAO-C-N-ETN-05-23-24/10375900081520 Dtd 14.07.2023 CA-ECR/ECRC/Civil/2023/0046 Dt 13.11.2023. Work started on 01-09-2023.
QWhat is the cost of this railway work?
The tendered cost of "Erection, launching & transportation of girder on remaining " is ₹3.05 Cr (against an estimate of ₹3.11 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Erection, launching & transportation of girder on remaining " is one of hundreds of railway works covered.